Market Notices

113306MARKET SYSTEMS16/01/2024 09:43:13 AM

CHG0082626 | Production | EMMS Production - FTP/Participant Intrface - Preventative maintenance

Change Number: CHG0082626
Notification issued to: Market Notice

Notification Type: Initial
Change Type: Expedited
Service/ Component: EMMS - Dispatch

Change Title: EMMS Production - FTP/Participant Intrface - Preventative maintenance.

Change Start Date & Time: 18/01/2024 13:15:00 AEST
Change End Date & Time: 18/01/2024 13:30:30 AEST
Outage Start Date & Time: 18/01/2024 13:23:00 AEST
Outage End Date & Time: 18/01/2024 13:24:00 AEST

Environment: Production

Participant Impact and Requirements: The maintenance activity is not expected to have any impact, however participants will briefly lose connectivity to the FTP/Intrface for no more than a minute on Thursday 18 January between 13:23 to 13:24 AEST

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.
113220MARKET SYSTEMS12/01/2024 09:23:21 AM

INC0124489 | RESOLVED | Issue with PD-PASA runs

AEMO ELECTRICITY MARKET NOTICE
SERVICE INTERRUPTION - RESOLVED
Please be informed that we had issue with Pre-Dispatch Projected Assessment of System Adequacy (PDPASA) service which has been restored now.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
113203MARKET SYSTEMS11/01/2024 11:33:50 AM

CHG0082517 | Production | Prod MSATS 50.0.4 LCCD Defect Release | CANCELLED

Change Number: CHG0082517
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Prod MSATS 50.0.4 LCCD Defect Release
Change Start Date & Time: 21/01/2024 10:00:00 AEST
Change End Date & Time: 21/01/2024 17:00:00 AEST
Outage Start Date & Time: 21/01/2024 10:00:00 AEST
Outage End Date & Time: 21/01/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
113131MARKET SYSTEMS09/01/2024 09:33:05 AM

CHG0082517 | Production | Prod MSATS 50.0.4 LCCD Defect Release

Change Number: CHG0082517
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Prod MSATS 50.0.4 LCCD Defect Release
Change Start Date & Time: 21/01/2024 10:00:00 AEST
Change End Date & Time: 21/01/2024 17:00:00 AEST
Outage Start Date & Time: 21/01/2024 10:00:00 AEST
Outage End Date & Time: 21/01/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
113064MARKET SYSTEMS05/01/2024 02:37:24 PM

CHG0082511 | Pre-Production | Pre-Prod MSATS 50.0.4 LCCD Defect Release

Change Number: CHG0082511
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS 50.0.4 LCCD Defect Release
Change Start Date & Time: 09/01/2024 13:00:00 AEST
Change End Date & Time: 09/01/2024 17:00:00 AEST
Outage Start Date & Time: 09/01/2024 13:00:00 AEST
Outage End Date & Time: 09/01/2024 15:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
113015MARKET SYSTEMS03/01/2024 01:57:46 PM

CHG0082504 | Pre-Production | Removal of support of TLS Version 1.1 and lower

Change Number: CHG0082504
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Market Network
Change Title: Removal of support of TLS Version 1.1 and lower
Change Start Date & Time: 14/02/2024 10:00:00 AEST
Change End Date & Time: 14/02/2024 14:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Pre-Production
Participant Impact and Requirements: Participants using TLS version 1.1 and lower, need to update their servers to use TLSv1.2 as a minimum. Failing to do so would impact the connectivity with AEMO. An outage is not expected but, there may be some minor interruptions during the change period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
112364RESERVE NOTICE14/12/2023 06:16:35 PM

Cancellation of Actual (LOR2) condition in the NSW region - 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the NSW region - 14/12/2023

The Actual LOR2 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112362 is cancelled at 1810 hrs 14/12/2023.

Manager NEM Real Time Operations
112362RESERVE NOTICE14/12/2023 06:00:52 PM

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 14/12/2023

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR2 condition is not forecast in Pre Dispatch

The capacity reserve required is 690 MW
The minimum reserve available is 678 MW

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement a AEMO intervention event.

Manager NEM Real Time Operations
112249MARKET SYSTEMS13/12/2023 02:02:59 PM

CHG0082097 | Completed | Production | P3062 Manifestly Incorrect Inputs (MII)? Production Release

Change Number: CHG0082097
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: EMMS - Dispatch
Change Title: P3062 Manifestly Incorrect Inputs (MII) Production Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm