Direction - SA region 25/02/2025
Direction - SA region 25/02/2025
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 25/02/2025.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 22/02/2025
Cancellation - AEMO Intervention Event - SA region 22/02/2025
Refer to Market Notice 124994
The AEMO Intervention Event and all associated directions are cancelled from 1530 hrs on 25/02/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 125073
Direction is cancelled from: 1530 hrs 25/02/2025
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 125072
Direction is cancelled from: 1500 hrs 25/02/2025
Manager NEM Real Time Operations
Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 125084
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 26/02/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1600 hrs 25/02/2025, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 26/02/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Tuesday, 25 February 2025
NON-CONFORMANCE VIC1 Region Tuesday, 25 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MOKOSF1
Duration: 25/02/2025 09:50 to 25/02/2025 11:00
Amount: 32 MW
Constraint: NC-V_MOKOSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 25 February 2025
NON-CONFORMANCE QLD1 Region Tuesday, 25 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: STAN-4
Duration: 25/02/2025 09:30 to 25/02/2025 10:20
Amount: -18 MW
Constraint: NC-Q_STAN-4
Auto-generated on behalf of Manager NEM Real Time Operations
Yass to Wagga control scheme change - removal system normal constraint equations in NSW managing 990, 991 and 970 132kV lines
Transgrid has advised AEMO of an update to the Yass overload trip scheme. The scheme is normally armed managing line flow on 990, 991, 970 132kV lines and it is now operating both directions of flow from Wagga to Yass.
Based on this advice, the following constraint equations will be removed from the NSW system normal constraint sets N-NIL and N-NIL_991, effective immediately.
N>>NIL_970_051
N>>NIL_990_051
N>>NIL_991_051
Ben Blake