120769PRICES UNCHANGED21/11/2024 06:15:24 PM

[EventId:202411211750_confirmed] Prices for interval 21-Nov-2024 17:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1815 hrs on 21 November 2024

PRICES ARE NOW CONFIRMED for trading interval 21-Nov-2024 17:50.

In accordance with Market Notice 120762 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120757RESERVE NOTICE21/11/2024 03:44:56 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120675 has been updated at 1400 hrs 21/11/2024 to the following:

From 1700 hrs to 1900 hrs 26/11/2024.
The forecast capacity reserve requirement is 1107 MW.
The minimum capacity reserve available is 583 MW.


AEMO Operations
     
120756RESERVE NOTICE21/11/2024 03:46:03 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:

From 1730 hrs to 2000 hrs 27/11/2024.
The forecast capacity reserve requirement is 1116 MW.
The minimum capacity reserve available is 1033 MW.


AEMO Operations
     
120755RESERVE NOTICE21/11/2024 03:49:35 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 25/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:

From 1800 hrs to 1830 hrs 25/11/2024.
The forecast capacity reserve requirement is 1120 MW.
The minimum capacity reserve available is 884 MW.


AEMO Operations

     
120754RESERVE NOTICE21/11/2024 03:50:40 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120719 has been updated at 1400 hrs 21/11/2024 to the following:

1. From 1430 hrs to 1500 hrs 27/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1232 MW.

2. From 1530 hrs to 2030 hrs 27/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 986 MW.


AMEO Operations
     
120753RESERVE NOTICE21/11/2024 03:48:37 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120718 has been updated at 1400 hrs 21/11/2024 to the following:

1. From 1130 hrs to 1400 hrs 26/11/2024.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 680 MW.

2. From 1900 hrs to 2030 hrs 26/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 788 MW.


AEMO Operations
     
120752RESERVE NOTICE21/11/2024 03:51:41 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

From 1730 hrs to 1830 hrs 24/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1273 MW.


AEMO Operations

     
120751RESERVE NOTICE21/11/2024 03:47:11 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120717 has been updated at 1400 hrs 21/11/2024 to the following:

1. From 1400 hrs to 1600 hrs 25/11/2024.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 680 MW.

2. From 1900 hrs to 2030 hrs 25/11/2024.
The forecast capacity reserve requirement is 1460 MW.
The minimum capacity reserve available is 730 MW.



AEMO Operations
     
120724GENERAL NOTICE21/11/2024 12:37:48 PM

Network Augmentation Commissioned - QLD Region - 21/11/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 21/11/2024

Commissioned:

Belmont No.2 275 kV 150 MVar reactor