Update to system strength requirements in North Queensland
Refer to market notice 121468
AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
The system normal equations have been revised to remove Gladstone >=1 requirement.
A revision to the constraint equations will be implemented at 1200 hrs on Tuesday 4th February 2025.
The new combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice
This advice contains all the combinations for Queensland for system normal cases. Additional information has been included in the limit advice to clarify the requirement to disconnect all inverters/turbines under certain system conditions.
The constraint equation in the Q-NIL set of the form below will be modified:
-Q_NIL_STRGTH_xxxx
-Q_NIL_STRGTH_xxxx_I
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1900 hrs 03/02/2025 to 2000 hrs 03/02/2025.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 243 MW.
AEMO is seeking a market response.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 124033 is cancelled at 1015 hrs 03/02/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1830 hrs 03/02/2025 to 1930 hrs 03/02/2025.
The forecast capacity reserve requirement is 371 MW.
The minimum capacity reserve available is 251 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No.124021 is cancelled at 2345 hrs 02/02/2025.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 03/02/2025
The Forecast LOR2 condition in the VIC region advised in AEMO Electricity Market Notice No.124022 is cancelled at 2345 hrs 02/02/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 03/02/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:
[1.] From 1830 hrs 03/02/2025 to 1900 hrs 03/02/2025.
The forecast capacity reserve requirement is 823 MW.
The minimum capacity reserve available is 801 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/02/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1830 hrs 03/02/2025 to 1930 hrs 03/02/2025.
The forecast capacity reserve requirement is 404 MW.
The minimum capacity reserve available is 333 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
[EventId:202502011830_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 01 February 2025 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 1 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 1 February 2025.
Refer to market notice: 123990
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1830 hrs on 1 February 2025.
This is an AEMO autogenerated Market Notice.