122198MARKET INTERVENTION18/12/2024 03:58:19 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122111

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1530 hrs 19/12/2024.

The direction update is issued at 1600 hrs 18/12/2024.

Manager NEM Real Time Operations
     
122117RESERVE NOTICE17/12/2024 05:44:06 PM

Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) condition in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122113 is cancelled at 1745 hrs 17/12/2024.

Manager NEM Real Time Operations
     
122113RESERVE NOTICE17/12/2024 03:44:28 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 17/12/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1530 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 1340 MW
The minimum capacity reserve available is 1082 MW

Manager NEM Real Time Operations
     
122111MARKET INTERVENTION17/12/2024 04:31:37 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122013

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 19/12/2024.

The direction update is issued at 1630 hrs 17/12/2024.

Manager NEM Real Time Operations
     
122110MARKET INTERVENTION17/12/2024 04:30:15 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 122012

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 19/12/2024.

The direction update is issued at 1630 hrs 17/12/2024.

Manager NEM Real Time Operations
     
122049RESERVE NOTICE16/12/2024 06:40:21 PM

Cancellation of Actual (LOR1) condition in the NSW region - 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 16/12/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.122029 is cancelled at 1835 hrs 16/12/2024.

Manager NEM Real Time Operations
     
122047MARKET SYSTEMS16/12/2024 06:07:34 PM

CHG0100502 | Production | Planned maintenance affecting the AEMO Market Network.

Change Number: CHG0100502
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MarketNet
Change Title: Planned maintenance affecting the AEMO Market Network ***Outage Updated***
Change Start Date & Time: 19/12/2024 07:00:00 AEST
Change End Date & Time: 20/12/2024 17:00:00 AEST
Outage 1 Start Date & Time: 19/12/2024 09:12:00 AEST
Outage 1 End Date & Time: 19/12/2024 09:13:00 AEST
Outage 2 Start Date & Time: 19/12/2024 15:12:00 AEST
Outage 2 End Date & Time: 19/12/2024 15:13:00 AEST

Environment: Production
Participant Impact and Requirements: Planned maintenance will be conducted on the 19th of December 2024, between 07:00AM and 05:00PM AEST on the core network infrastructure within the AEMO Market Network in Brisbane.

During there change, there will be two instances of 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Sydney will not be affected during this time. AEMO recommends that all market participants with site to site VPN connections currently connected via Brisbane, to switch these connections to the Sydney site as a precaution.

Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Sydney site and do not need to take any action.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .

     
122029RESERVE NOTICE16/12/2024 05:21:43 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/12/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 1340 MW
The minimum capacity reserve available is 1297 MW

Manager NEM Real Time Operations
     
122013MARKET INTERVENTION16/12/2024 04:32:34 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122011


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1630 hrs 16/12/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0200 hrs 17/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 18/12/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     