Filter by category
Filter by Date
[EventId:202411251605_review] Prices for interval 25-Nov-2024 16:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 25 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Nov-2024 16:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
INC0138597 - ALERT - EMMS
AEMO is experiencing a service interruption relating to the Electricity Market Management System service.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
Inter-Regional Transfer limit variation - Murraylink
Inter-Regional Transfer limit variation - Murraylink
There has been an unplanned outage of Murraylink.
The following constraint set was invoked at 1405 hrs 25/11/2024
I-ML_ZERO
The constraint set contains the following interconnector on the left hand side.
V-S-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024
Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024
At 1911 hrs 22/11/2024 there was an unplanned outage of the No.2 leg of Directlink.
The following constraint set(s) invoked at 1920 hrs 22/11/2024
N-X_MBTE_2
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 2 Leg of Directlink .
The following constraint set was invoked at 1720 hrs 22/11/2024
N-X_MBTE_2
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
[EventId:202411221145_review] Prices for interval 22-Nov-2024 11:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1140 hrs on 22 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Nov-2024 11:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411221140_review] Prices for interval 22-Nov-2024 11:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1135 hrs on 22 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Nov-2024 11:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411221135_review] Prices for interval 22-Nov-2024 11:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 22 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Nov-2024 11:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411221130_review] Prices for interval 22-Nov-2024 11:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1125 hrs on 22 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Nov-2024 11:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.