Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 29/10/2024
Refer AEMO Electricity Market Notice 119610
Constraint set CA_SYDS_5632AA58 was invoked from 0940 hrs until 10:45 hrs 29/10/2024.
This constraint set contains equations with the following interconnector on the LHS;
V-SA
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 29/10/2024
In order to maintain the power system in a secure operating state in the SA region, AEMO has invoked automated constraint set CA_SYDS_5632AA58 from 0940 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
V-SA
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - [outage element] - NSW region - 24/10/2024
Inter-regional transfer limit variation - [outage element] - NSW region - 24/10/2024
At 1435 hrs 24/10/2024 there was an unplanned outage of Directlink cable 1 and cable 3 (note cable 2 was on a prior outage).
The following constraint set(s) invoked at 1445 hrs 24/10/2024
N-X_MBTE_3
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 23/10/2024
In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_SYDS_562A9792 from 0635 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
V-S-MNSP1
V-SA
VIC1-NSW1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Tamworth No 1 330 kV bus and Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/10/2024
Tamworth No 1 330 kV bus and Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/10/2024
A planned outage of Tamworth No 1 330 kV bus in the NSW region was scheduled from 1100 hrs 18/10/2024 to 1700 hrs 20/10/2024.
A planned outage of Tamworth - Armidale No. 86 330 kV Line in the NSW region was scheduled from 0500 hrs 09/10/2024 to 1700 hrs 20/10/2024.
The outage has been completed by 1250 hrs 19/10/2024.
Constraint set(s) invoked:
N-ARTW_86
N-LDTW_84
N-TW_SVC
N-TW_330_BUS1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Non-credible contingency event - VIC region - 18/10/2024
Non-credible contingency event - VIC region - 18/10/2024
At 1525 hrs the Rowville - Yallourn No. 7 220 kV Line and the Rowville - Yallourn No. 8 220 kV Line tripped and auto-reclosed.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Brinkworth- Red Hill- Bungama 132kV lines - SA region - 17/10/2024
Inter-regional transfer limit variation - Brinkworth- Red Hill- Bungama 132kV lines - SA region - 17/10/2024
At 1846 hrs 17/10/2024 there was an unplanned outage of Brinkworth- Red Hill- Bungama 132kV lines.
The following constraint set(s) invoked at 1855 hrs 17/10/2024
S-BRBG
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Hummocks - Bungama 132kV line - SA region - 17/10/2024
Inter-regional transfer limit variation - Hummocks - Bungama 132kV line - SA region - 17/10/2024
At 1842 hrs 17/10/2024 there was an unplanned outage of Hummocks - Bungama 132kV line.
The following constraint set(s) invoked at 1850 hrs 17/10/2024
S-HUBG
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Blyth West - Munno Para 275kV line- SA region - 17/10/2024
Inter-regional transfer limit variation - Blyth West - Munno Para 275kV line - SA region - 17/10/2024
At 1848 hrs 17/10/2024 there was an unplanned outage of Blyth West - Munno Para 275kV line.
The following constraint set(s) invoked at 1855 hrs 17/10/2024
S-BWMP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations