Market Notices

122345PRICES SUBJECT TO REVIEW21/12/2024 12:31:48 PM

[EventId:202412211235_review] Prices for interval 21-Dec-2024 12:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1230 hrs on 21 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 21-Dec-2024 12:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122318INTER-REGIONAL TRANSFER20/12/2024 03:28:59 PM

Inter-regional transfer limit variation - South East No.61 Capacitor 275kV - SA region - 20/12/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South East No.61 Capacitor 275kV - SA region - 20/12/2024

At 1445 hrs 20/12/2024 there was an unplanned outage of South East No.61 Capacitor 275kV.

The following constraint set(s) invoked at 1445 hrs 20/12/2024
S-SE_1CP

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
122317INTER-REGIONAL TRANSFER20/12/2024 03:16:23 PM

Update Inter-regional transfer limit variation - Lismore SVC 132kV - NSW region - 20/12/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lismore SVC 132kV - NSW region - 20/12/2024

At 1300 hrs 20/12/2024 there was a short notice outage of Lismore SVC 132kV.

The following constraint set(s) invoked at 1300 hrs 20/12/2024
N-LS_VC1

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
122310INTER-REGIONAL TRANSFER20/12/2024 01:01:43 PM

Inter-regional transfer limit variation - [outage element] - NSW region - 20/12/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - [outage element] - NSW region - 20/12/2024

At 1300 hrs 20/12/2024 there was a short notice outage of [outage element].

The following constraint set(s) invoked at 1300 hrs 20/12/2024
N-LS_VC1

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
122306GENERAL NOTICE20/12/2024 10:33:57 AM

NEM Local Temperature Alerts for QLD from 20 Dec 2024 to 24 Dec 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

QLD
Rockhampton Ap (39+ Deg C): 24th Dec

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
122296PRICES SUBJECT TO REVIEW20/12/2024 07:25:19 AM

[EventId:202412200730_review] Prices for interval 20-Dec-2024 07:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0725 hrs on 20 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 20-Dec-2024 07:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122295PRICES SUBJECT TO REVIEW20/12/2024 07:20:21 AM

[EventId:202412200725_review] Prices for interval 20-Dec-2024 07:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0720 hrs on 20 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 20-Dec-2024 07:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122294PRICES SUBJECT TO REVIEW20/12/2024 07:15:21 AM

[EventId:202412200720_review] Prices for interval 20-Dec-2024 07:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0715 hrs on 20 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 20-Dec-2024 07:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122293PRICES SUBJECT TO REVIEW20/12/2024 07:10:22 AM

[EventId:202412200715_review] Prices for interval 20-Dec-2024 07:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0710 hrs on 20 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 20-Dec-2024 07:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm