Market Notices

121258RESERVE NOTICE29/11/2024 04:16:55 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1630 hrs 29/11/2024 to 1700 hrs 29/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1363 MW.

Manager NEM Real Time Operations
     
121257RECLASSIFY CONTINGENCY29/11/2024 03:57:41 PM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 29/11/2024 15:57 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
     
121250PRICES SUBJECT TO REVIEW29/11/2024 03:45:16 PM

[EventId:202411291550_review] Prices for interval 29-Nov-2024 15:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1545 hrs on 29 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 15:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121249PRICES SUBJECT TO REVIEW29/11/2024 03:40:15 PM

[EventId:202411291545_review] Prices for interval 29-Nov-2024 15:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1540 hrs on 29 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 15:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121248PRICES SUBJECT TO REVIEW29/11/2024 03:36:21 PM

[EventId:202411291540_review] Prices for interval 29-Nov-2024 15:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1535 hrs on 29 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 15:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121246PRICES SUBJECT TO REVIEW29/11/2024 03:30:12 PM

[EventId:202411291535_review] Prices for interval 29-Nov-2024 15:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1530 hrs on 29 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 15:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121245PRICES SUBJECT TO REVIEW29/11/2024 03:26:31 PM

[EventId:202411291530_review] Prices for interval 29-Nov-2024 15:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1525 hrs on 29 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 15:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121244PRICES SUBJECT TO REVIEW29/11/2024 03:25:11 PM

[EventId:202411291525_review] Prices for interval 29-Nov-2024 15:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1520 hrs on 29 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Nov-2024 15:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
121243RECLASSIFY CONTINGENCY29/11/2024 03:19:22 PM

Cancellation of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line

Cancellation time: 29/11/2024 15:19

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 121236

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm