Market Notices

116939RECLASSIFY CONTINGENCY11/06/2024 02:19:06 PM

Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Cancellation time: 11/06/2024 14:19

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 116937

Auto-generated on behalf of Manager NEM Real Time Operations
116937RECLASSIFY CONTINGENCY11/06/2024 01:17:02 PM

Reclassification of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Duration: 11/06/2024 13:16 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
116933RESERVE NOTICE11/06/2024 01:09:29 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 12/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 0830 hrs 12/06/2024 to 0900 hrs 12/06/2024.
The forecast capacity reserve requirement is 421 MW.
The minimum capacity reserve available is 393 MW.

[2.] From 0930 hrs 12/06/2024 to 1000 hrs 12/06/2024.
The forecast capacity reserve requirement is 419 MW.
The minimum capacity reserve available is 407 MW.

Manager NEM Real Time Operations
116926RESERVE NOTICE10/06/2024 05:51:08 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1700 hrs 17/06/2024 to 2100 hrs 17/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1530 MW.

Manager NEM Real Time Operations
116910RESERVE NOTICE07/06/2024 03:46:01 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 13/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 116905 is cancelled at 1400 hrs 07/06/2024.

No LOR condition is currently forecast in the STPASA period.

AEMO Operations
116905RESERVE NOTICE06/06/2024 02:54:08 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 13/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 1730 hrs to 2100 hrs 13/06/2024.
The forecast capacity reserve requirement is 439 MW.
The minimum capacity reserve available is 382 MW.


AEMO Operations

116903RECLASSIFY CONTINGENCY06/06/2024 01:34:54 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 06/06/2024 13:34

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 116902

Auto-generated on behalf of Manager NEM Real Time Operations
116902RECLASSIFY CONTINGENCY06/06/2024 12:31:05 PM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 06/06/2024 12:30 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
116890PRICES SUBJECT TO REVIEW04/06/2024 06:55:22 PM

[EventId:202406041900_review] Prices for interval 04-Jun-2024 19:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1855 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 19:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.