112746INTER-REGIONAL TRANSFER25/12/2023 09:46:39 PM

Inter-regional transfer limit variation - Greenbank - Mudgeeraba 835 275 kV line - QLD region - 25/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Greenbank - Mudgeeraba 835 275 kV line - QLD region - 25/12/2023

At 2102 hrs 25/12/2023 there was an unplanned outage of Greenbank - Mudgeeraba 835 275 kV line

Constraint set(s) invoked: Q-GBMU_835_836 from 2105 hrs

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q_MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112745INTER-REGIONAL TRANSFER25/12/2023 09:37:47 PM

Inter-regional transfer limit variation - Greenbank - Molendinar 8824 275 kV line - QLD region - 25/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Greenbank - Molendinar 8824 275 kV line - QLD region - 25/12/2023

At 2057 hrs 25/12/2023 there was an unplanned outage of Greenbank - Molendinar 8824 275 kV line

The outage has been returned to service at 2125 hrs 25/12/2023

Constraint set(s) invoked: Q-GBMO_8824_8825 from 2105 hrs to 2125 hrs


This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q_MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112621INTER-REGIONAL TRANSFER23/12/2023 12:38:04 PM

Inter-regional transfer limit variation - Palmerston - Hadspen 220 kV Line - TAS region - 23/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Palmerston - Hadspen 220 kV Line - TAS region - 23/12/2023

A planned outage of Palmerston - Hadspen 220 kV Line in the TAS region was scheduled from 1000 hrs 23/12/2023 to 1500 hrs 23/12/2023.

The outage has been completed and returned to service at 1045 hrs 23/12/2023

Constraint set(s) invoked:
T-HAPM_220

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V- MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112613INTER-REGIONAL TRANSFER23/12/2023 06:39:17 AM

Inter-regional transfer limit variation - [outage element] - NSW region - 23/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - [outage element] - NSW region - 23/12/2023


A planned outage of KEMPS CREEK No 2 525/345/34 kV Transformer in the NSW region was scheduled from 0600 hrs 23/12/2023 to 1200 hrs 23/12/2023.

The outage has been cancelled.

The following constraint set(s) invoked at 0600 hrs 23/12/2023
N-KC_TX

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q_MNSP1
NSW1-QLD1
VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112590INTER-REGIONAL TRANSFER22/12/2023 01:01:28 PM

Inter-regional transfer limit variation - Palmerston - Hadspen 2 220kV line - TAS region - 22/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Palmerston - Hadspen 2 220kV line - TAS region - 22/12/2023

At 1300 hrs 22/12/2023 there was a short notice outage of Palmerston - Hadspen 2 220kV line.

Constraint set(s) invoked: T-HAPM_220


This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V - MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112433INTER-REGIONAL TRANSFER17/12/2023 06:09:07 AM

Inter-regional transfer limit variation: Hazelwood - South Morang No 1 500 kV Line (VIC) - Voltage Control

AEMO ELECTRICITY MARKET NOTICE

The Hazelwood - South Morang No 1 500 kV Line has been de-energised to manage voltages in the Victoria region.

The following constraint set was invoked at 0600 hrs 17/12/2023

V-HWSM

The constraint set contains equations with the following interconnectors on the LHS.

T-V-MNSP
V-S-MNSP1
V-SA
VIC1-NSW1

Refer to AEMO Network Outage Scheduler (NOS) for return to service details

Manager NEM Real Time Operations
112432INTER-REGIONAL TRANSFER17/12/2023 05:48:19 AM

Inter-regional transfer limit variation - Sydney West - Vineyard No 29 330kV line - NSW region - 17/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Sydney West - Vineyard No 29 330kV line - NSW region - 17/12/2023

At 0545 hrs 17/12/2023 there was a short notice outage of Sydney West - Vineyard No 29 330kV line.

Constraint set(s) invoked: N-SWVY_29

The following constraint set(s) invoked at 0545 hrs 17/12/2023
N-SWVY_29

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112366RESERVE NOTICE14/12/2023 07:41:53 PM

Cancellation of Actual (LOR1) condition in the NSW region - 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 14/12/2023

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112357 is cancelled at 1940 hrs 14/12/2023.

Manager NEM Real Time Operations
112357RESERVE NOTICE14/12/2023 04:50:22 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/12/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/12/2023

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 1377 MW
The minimum capacity reserve available is 874 MW