CHG0087945 | Production | Planned System Maintenance activity
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMS NEM - Network Outage Scheduler (NOS)
Change Title: Planned System Maintenance activity.
Change Start Date & Time: 10/04/2024 11:00:00 AEST
Change End Date & Time: 10/04/2024 12:00:00 AEST
Outage Start Date & Time: 10/04/2024 11:00:00 AEST
Outage End Date & Time: 10/04/2024 12:00:00 AEST
Environment: Production
Participant Impact and Requirements: Network Outage Schedular (NOS) will be out of service during the maintenance activity. Please log off from NOS website during the outage. Users will have to log back in once the outage is completed. Please contact your NOS admin or AEMO support hub if your NOS account has been locked out after this change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.
CHG0087653 | Completed | Production | Prod eMDM Maintenance
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management
Change Title: Prod eMDM Maintenance
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0086184 | Completed | Production | NSW Internet Router Refresh
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: NSW Internet Router Refresh
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0087334 | Completed | Production | Brisbane MarketNet Firewall Refresh
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Firewall
Change Title: Brisbane MarketNet Firewall Refresh
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0087775 | Completed | Pre-Production | Pre-Prod MSATS Lifecycle Maintenance
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)_PreProd
Change Title: Pre-Prod MSATS Lifecycle Maintenance
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Inter-regional transfer limit variation - Pelican Point to Parafield Gardens West 275kV Line - SA region - 02/04/2024
Inter-regional transfer limit variation - Pelican Point to Parafield Gardens West 275kV Line - SA region - 02/04/2024
A planned outage of Pelican Point to Parafield Gardens West 275kV Line in the SA region was scheduled from 0730 hrs 02/04/2024 to 1530 hrs 02/04/2024.
The outage has been cancelled at 0718 hrs 02/04/2024
Constraint set(s) revoked: S-PGPP, S-PPPG_PELPT
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
CHG0087932 | Completed | Pre-Production | Planned System Maintenance in Preproduction for Web Exchanger
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: DWGM - Web Exchanger
Change Title: Planned System Maintenance in Preproduction for Web Exchanger
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0087932 | Pre-Production | Planned System Maintenance in Preproduction for Web Exchanger
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: DWGM - Web Exchanger
Change Title: Planned System Maintenance in Preproduction for Web Exchanger
Change Start Date & Time: 28/03/2024 10:00:00 AEST
Change End Date & Time: 28/03/2024 17:00:00 AEST
Outage Start Date & Time: 28/03/2024 14:00:00 AEST
Outage End Date & Time: 28/03/2024 15:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Access to WEX will not be available during outage window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0087908 | Pre-Production | Pre-Prod MSATS Lifecycle Maintenance
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)_PreProd
Change Title: Pre-Prod MSATS Lifecycle Maintenance
Change Start Date & Time: 27/03/2024 19:00:00 AEST
Change End Date & Time: 01/04/2024 20:00:00 AEST
Outage Start Date & Time: 27/03/2024 19:00:00 AEST
Outage End Date & Time: 01/04/2024 21:18:14 AEST
Environment: Pre-Production
Participant Impact and Requirements: MSATS (preprod), CDR (preprod) and CDP (preprod) will be unavailable daily from today 27th March between 19:00 - 20:00 Market Time (AEST) until Monday 1st April
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any