Market Notices

113131MARKET SYSTEMS09/01/2024 09:33:05 AM

CHG0082517 | Production | Prod MSATS 50.0.4 LCCD Defect Release

Change Number: CHG0082517
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Prod MSATS 50.0.4 LCCD Defect Release
Change Start Date & Time: 21/01/2024 10:00:00 AEST
Change End Date & Time: 21/01/2024 17:00:00 AEST
Outage Start Date & Time: 21/01/2024 10:00:00 AEST
Outage End Date & Time: 21/01/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
113064MARKET SYSTEMS05/01/2024 02:37:24 PM

CHG0082511 | Pre-Production | Pre-Prod MSATS 50.0.4 LCCD Defect Release

Change Number: CHG0082511
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS 50.0.4 LCCD Defect Release
Change Start Date & Time: 09/01/2024 13:00:00 AEST
Change End Date & Time: 09/01/2024 17:00:00 AEST
Outage Start Date & Time: 09/01/2024 13:00:00 AEST
Outage End Date & Time: 09/01/2024 15:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
113015MARKET SYSTEMS03/01/2024 01:57:46 PM

CHG0082504 | Pre-Production | Removal of support of TLS Version 1.1 and lower

Change Number: CHG0082504
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Market Network
Change Title: Removal of support of TLS Version 1.1 and lower
Change Start Date & Time: 14/02/2024 10:00:00 AEST
Change End Date & Time: 14/02/2024 14:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Pre-Production
Participant Impact and Requirements: Participants using TLS version 1.1 and lower, need to update their servers to use TLSv1.2 as a minimum. Failing to do so would impact the connectivity with AEMO. An outage is not expected but, there may be some minor interruptions during the change period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
112793POWER SYSTEM EVENTS27/12/2023 12:04:43 AM

Non-credible contingency event - QLD region - 26/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 26/12/2023

At 2345 hrs the Strathmore Clare South 7208 and the Strathmore Clare South Tee King Creek 7128 132kV lines tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
112579POWER SYSTEM EVENTS21/12/2023 03:12:07 PM

Non-credible contingency event - QLD region - 21/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 21/12/2023

At 1424 hrs the H14 Middle Ridge 275 kV circuit breakers 5432 and 5422 tripped. This offloaded the H14 Middle Ridge No.2 and No.3 275/110 kV transformers.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
112249MARKET SYSTEMS13/12/2023 02:02:59 PM

CHG0082097 | Completed | Production | P3062 Manifestly Incorrect Inputs (MII)? Production Release

Change Number: CHG0082097
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: EMMS - Dispatch
Change Title: P3062 Manifestly Incorrect Inputs (MII) Production Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
112247POWER SYSTEM EVENTS13/12/2023 01:43:17 PM

Non-credible contingency event - TAS region - 13/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 13/12/2023

At 1324 hrs the Hadspen - Palmerston No.3 & No.4 110 kV lines tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
112196MARKET SYSTEMS12/12/2023 07:05:08 AM

CHG0082097 | Production | P3062 Manifestly Incorrect Inputs (MII)? Production Release

Change Number: CHG0082097
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: P3062 Manifestly Incorrect Inputs (MII) Production Release
Change Start Date & Time: 12/12/2023 08:00:00 AEST
Change End Date & Time: 13/12/2023 17:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Under this change , AEMO will install an updated version of a key Dispatch application (NEMDE Solutionloader) used in Production for Dispatch, 5-Minute Pre-dispatch, Pre-dispatch, and 7-Day Pre-dispatch.

Changes include:
o Extension of Automated MII Procedures to include detection of FCAS MIIs using an FCAS requirement threshold.

No outages or delays expected. AEMO will advise once complete.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
112187POWER SYSTEM EVENTS11/12/2023 04:04:48 PM

Update - Non-credible contingency event - SA region - 11/12/2023

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - SA region - 11/12/2023

Refer AEMO Electricity Market Notice 112181

At 1554 hrs the remaining Mintaro - Waterloo 132 kV Line was returned to service.

The following constraint set(s) revoked:
S-X-MNWT+CB

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm