115653NON-CONFORMANCE15/03/2024 03:40:17 PM

NON-CONFORMANCE Region QLD1 Friday, 15 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 15 March 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 15/03/2024 15:20 to 15/03/2024 15:40
Amount: -16 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
115652INTER-REGIONAL TRANSFER15/03/2024 02:52:51 PM

Inter-Regional Transfer limit variation - Murraylink

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink

There has been an unplanned outage of the Murraylink interconnector.

The following constraint set was invoked at 1445 hrs 15/03/2024

I-ML_ZERO

The constraint set contains the following interconnector on the left hand side.

V-S-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
115627INTER-REGIONAL TRANSFER15/03/2024 06:31:39 AM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 15/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 15/03/2024

At 0600 hrs 15/03/2024 there was a short notice outage of Robertstown - Tungkillo No. 2 275 kV Line.
At 0615 hrs 15/03/2024 there was a short notice outage of Tungkillo - Para No. 1 275 kV Line.

In order to maintain the power system in a secure operating state in the SA region, AEMO has invoked the following automated constraint sets.

CA_SYDS_5505DC4C from 06:00 hrs until further notice

These constraint sets contains equations with the following interconnector on the LHS;

V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115626INTER-REGIONAL TRANSFER15/03/2024 05:10:47 AM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 15/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 15/03/2024

In order to maintain the power system in a secure operating state in the SA region, AEMO has invoked the following automated constraint sets.

CA_SYDS_5505D0BC from 04:40 hrs to 05:10 hrs
CA_SYDS_5505D516 from 04:55 hrs to 05:10 hrs

These constraint sets contains equations with the following interconnector on the LHS;

V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115625INTER-REGIONAL TRANSFER14/03/2024 11:49:03 PM

Inter-regional transfer limit variation - Robertstown - Tungkillo No. 1 275 kV Line - SA region - 14/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Robertstown - Tungkillo No. 1 275 kV Line - SA region - 14/03/2024

At 2307 hrs 14/03/2024 there was an unplanned outage of Robertstown - Tungkillo No. 1 275 kV Line.


The following constraint set(s) invoked at 2315 hrs 14/03/2024
S-RBTU

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115618INTER-REGIONAL TRANSFER14/03/2024 07:32:14 AM

Inter-regional transfer limit variation - Lismore 132kV SVC - NSW region - 14/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lismore 132kV SVC - NSW region - 14/03/2024

At 0800 hrs 14/03/2024 there was a short notice outage of Lismore 132kV SVC.

The following constraint set(s) invoked at 0800 hrs 14/03/2024
N-LS_VC1

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115551NON-CONFORMANCE09/03/2024 02:20:20 PM

NON-CONFORMANCE Region NSW1 Saturday, 9 March 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 9 March 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: DPNTBG1, DPNTBL1
Aggregate Dispatch Group: DPNTBESS_ADG1
Duration: 09/03/2024 14:10 to 09/03/2024 14:20
Amount: 22 MW
Constraint: NC-N_DPNTBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
115547INTER-REGIONAL TRANSFER08/03/2024 04:16:46 PM

Inter-regional transfer limit variation - South Pine SVC - QLD region - 08/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South Pine SVC - QLD region - 08/03/2024

At 1605 hrs 08/03/2024 there was an unplanned outage of South Pine SVC.

The following constraint set(s) invoked at 1610 hrs 08/03/2024
Q-SP_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115511INTER-REGIONAL TRANSFER06/03/2024 12:23:08 PM

Inter-regional transfer limit variation - Moorabool Sydenham No2 500 kV line - Vic region - 06/03/2024

AEMO ELECTRICITY MARKET NOTICE

At 1210 hrs 06/03/2024 in the Victoria region, the Moorabool Sydenham No2 500 kV line returned to service on temporary towers.

Constraint set changes.

Revoked:
V-MLSY_NOEMTT_R

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1
V-SA
V-S-MNSP1
VIC1- NSW1

Refer Market Notices 114577, 114768, 114686, 114770 and 115120.

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm