Market Notices

117080RESERVE NOTICE20/06/2024 12:48:26 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.117074 has been updated at 1239 hrs to the following:

[1.] From 1730 hrs 20/06/2024 to 1930 hrs 20/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1349 MW.


Manager NEM Real Time Operations
117079RESERVE NOTICE19/06/2024 06:47:26 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117073 is cancelled at1845 hrs 19/06/2024

Manager NEM Real Time Operations
117074RESERVE NOTICE19/06/2024 03:46:45 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.117067 has been updated at 1515 hrs to the following:

[1.] From 1730 hrs 20/06/2024 to 1900 hrs 20/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1541 MW.

Manager NEM Real Time Operations
117073RESERVE NOTICE19/06/2024 03:45:40 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.117055 has been updated at 1515 hrs to the following:

[1.] From 1800 hrs 19/06/2024 to 1900 hrs 19/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1619 MW.

Manager NEM Real Time Operations
117072RESERVE NOTICE19/06/2024 04:02:03 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 22/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117052 is cancelled at 1400 hrs 19/06/2024.

AEMO Operations
117071RESERVE NOTICE19/06/2024 04:04:46 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 21/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117051 has been updated at 1400 hrs 19/06/2024 to the following:

1. From 1730 hrs to 1900 hrs 21/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1404 MW.

AEMO Operations
117067RESERVE NOTICE19/06/2024 01:24:23 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 0800 hrs 20/06/2024 to 0830 hrs 20/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1358 MW.

[2.] From 1730 hrs 20/06/2024 to 1900 hrs 20/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1586 MW.


Manager NEM Real Time Operations
117059RESERVE NOTICE18/06/2024 06:45:58 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117048 is cancelled at1845 hrs 18/06/2024

Manager NEM Real Time Operations
117055RESERVE NOTICE18/06/2024 04:20:33 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.117046 has been updated at 1615 hrs to the following:

[1.] From 1730 hrs 19/06/2024 to 1930 hrs 19/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1521 MW.

Manager NEM Real Time Operations