118409RESERVE NOTICE23/09/2024 05:21:24 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

From 1900 hrs 24/09/2024 to 1930 hrs 24/09/2024.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 335 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
118406MARKET SYSTEMS23/09/2024 03:44:02 PM

CHG0098666 | Production | Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Number: CHG0098666

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Cisco IP Phone

Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Start Date & Time: 08/09/2024 00:00:00 AEST

Change End Date & Time: 08/09/2024 06:00:00 AEST

Outage Start Date & Time:

Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: Outage Duration:
3 x 15 Minutes

Impacts:

Reduced redundancy for Inbound and Outbound Calls (automatically rerouted via Perth).

Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .




118405MARKET SYSTEMS23/09/2024 03:36:16 PM

CHG0098660 | Production | Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Number: CHG0098660

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Cisco IP Phone

Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Start Date & Time: 24/09/2024 00:00:00 AEST

Change End Date & Time: 24/09/2024 06:00:00 AEST

Outage Start Date & Time:

Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: Outage Duration:
1 x 3 Hours

Impacts:
Reduced redundancy for Inbound and Outbound Calls (automatically rerouted via Perth).

Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .

118391RESERVE NOTICE23/09/2024 07:12:59 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118390 is cancelled at 07:15 hrs 23/09/2024.

Manager NEM Real Time Operations
118390RESERVE NOTICE23/09/2024 06:13:09 AM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 2000 hrs 23/09/2024 to 2030 hrs 23/09/2024.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 308 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
118388RESERVE NOTICE23/09/2024 05:54:01 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118387 is cancelled at 05:40 hrs 23/09/2024.

Manager NEM Real Time Operations
118387RESERVE NOTICE23/09/2024 05:16:09 AM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 2000 hrs 23/09/2024 to 2030 hrs 23/09/2024.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 279 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
118384RESERVE NOTICE22/09/2024 10:45:15 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118382 is cancelled at 22:40 hrs 22/09/2024.

Manager NEM Real Time Operations
118382RESERVE NOTICE22/09/2024 10:30:45 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1930 hrs 23/09/2024 to 2000 hrs 23/09/2024.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 322 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm