Market Notices

117132POWER SYSTEM EVENTS25/06/2024 10:20:35 AM

Non-credible contingency event - NSW region - 25/06/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 25/06/2024

At 0901 hrs the Sydney West No.1 330 kV SVC tripped during switching for planned outage of Sydney West No.4 330/132 kV transformer.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
117131NON-CONFORMANCE25/06/2024 09:50:20 AM

NON-CONFORMANCE Region QLD1 Tuesday, 25 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 25 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 25/06/2024 09:35 to 25/06/2024 09:50
Amount: -40 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
117125NON-CONFORMANCE24/06/2024 08:21:08 PM

NON-CONFORMANCE Region QLD1 Monday, 24 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 24 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 24/06/2024 18:30 to 24/06/2024 20:20
Amount: 49 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
117124NON-CONFORMANCE24/06/2024 08:20:17 PM

NON-CONFORMANCE Region QLD1 Monday, 24 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 24 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 24/06/2024 19:30 to 24/06/2024 20:20
Amount: -42 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
117121MARKET SYSTEMS24/06/2024 05:25:07 PM

CHG0090646 | Completed | Production | Planned maintenance affecting the AEMO Market Network.

Change Number: CHG0090646

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Market Network

Change Title: Planned maintenance affecting the AEMO Market Network.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
117115MARKET SYSTEMS24/06/2024 01:57:11 PM

CHG0090585 | Completed | Production | Dispatch Applications Upgrade

Change Number: CHG0090585

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: EMMS - Dispatch

Change Title: Dispatch Applications Upgrade

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
117113NON-CONFORMANCE24/06/2024 07:00:21 AM

NON-CONFORMANCE Region QLD1 Monday, 24 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 24 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 24/06/2024 06:40 to 24/06/2024 07:00
Amount: 19 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
117111NON-CONFORMANCE23/06/2024 08:00:16 PM

NON-CONFORMANCE Region QLD1 Sunday, 23 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 23 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 23/06/2024 19:05 to 23/06/2024 20:00
Amount: -35 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
117105NON-CONFORMANCE23/06/2024 12:55:20 PM

NON-CONFORMANCE Region QLD1 Sunday, 23 June 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 23 June 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 23/06/2024 12:15 to 23/06/2024 12:55
Amount: -29 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm