Market Notices

118319GENERAL NOTICE19/09/2024 01:45:31 PM

Planned outage of Tailem Bend - South East 275 kV transmission line in the South Australia region beginning on 20/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Tailem Bend - South East No 1 275 kV line in the South Australian (SA) region is planned to be out of service from 2100 hrs on 20/09/2024 to 0530 hrs on 21/09/2024.

A credible contingency event during this planned outage could cause synchronous separation of the SA region from the rest of the NEM.

During this planned outage:
- Power transfer will be restricted across the VIC - SA interconnector (Heywood interconnector); and
- Post contingent FCAS will be sourced within SA following Separation event.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
118299RESERVE NOTICE16/09/2024 07:16:21 PM

Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 16/09/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.118298 is cancelled at 1915 hrs 16/09/2024.

Manager NEM Real Time Operations
118298RESERVE NOTICE16/09/2024 06:16:31 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/09/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/09/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1274 MW

Manager NEM Real Time Operations
118257SETTLEMENTS RESIDUE12/09/2024 04:55:27 PM

[EventId:202409121655_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 12 September 2024 16:55

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1655 hrs on 12 September 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 September 2024.

Refer to market notice: 118256

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1655 hrs on 12 September 2024.

This is an AEMO autogenerated Market Notice.
118256SETTLEMENTS RESIDUE12/09/2024 03:05:26 PM

[EventId:202409121505_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 12 September 2024 15:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1505 hrs on 12 September 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 September 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1505 hrs on 12 September 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
118248SETTLEMENTS RESIDUE12/09/2024 11:30:31 AM

[EventId:202409121130_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 12 September 2024 11:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1130 hrs on 12 September 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 September 2024.

Refer to market notice: 118247

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1130 hrs on 12 September 2024.

This is an AEMO autogenerated Market Notice.
118247SETTLEMENTS RESIDUE12/09/2024 10:35:23 AM

[EventId:202409121035_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 12 September 2024 10:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1035 hrs on 12 September 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 September 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1035 hrs on 12 September 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
118226GENERAL NOTICE10/09/2024 05:55:51 PM

Network Augmentation Commissioned - NSW Region - 10/09/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 10/09/2024

At 1750 hrs, the following equipment at Buronga 330 kV substation has been commissioned:

1) Buronga 330 kV A bus.
2) Buronga 330 kV B bus.
3) Buronga No 1 330 kV capacitor.
4) Buronga No 2 330 kV capacitor.
5) Buronga No 7 330/220 kV transformer.

Manager NEM Real Time Operations
118199SETTLEMENTS RESIDUE08/09/2024 08:00:22 PM

[EventId:202409082000_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 September 2024 20:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2000 hrs on 8 September 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 September 2024.

Refer to market notice: 118188

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2000 hrs on 8 September 2024.

This is an AEMO autogenerated Market Notice.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm