117561RESERVE NOTICE05/08/2024 06:21:59 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117548 has been updated at 1815 hrs to the following:

[1.] From 1930 hrs 05/08/2024 to 2130 hrs 05/08/2024.
The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 386 MW.

Manager NEM Real Time Operations
117547RESERVE NOTICE05/08/2024 04:27:39 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1900 hrs 05/08/2024 to 2200 hrs 05/08/2024.
The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 317 MW.

Manager NEM Real Time Operations
117503POWER SYSTEM EVENTS30/07/2024 07:07:11 AM

Non-credible contingency event - QLD region - 30/07/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 30/07/2024

At 0537 hrs the Darling Downs Power Station GT1, GT3 and and the steam turbine tripped from 484 MW.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
117501RESERVE NOTICE29/07/2024 05:49:35 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region [beginning] on 29/07/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117497 is cancelled at 0545 hrs 29/07/2024.

Manager NEM Real Time Operations
117500POWER SYSTEM EVENTS28/07/2024 05:14:14 PM

Update - Non-credible contingency event - QLD region - 27/07/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - QLD region - 27/07/2024

Refer AEMO Electricity Market Notice 117487

At 1702 hrs the H38 Goodna No. 2 275kV Bus and the H38 Goodna No. 1 275/132kV transformer was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
117499RESERVE NOTICE28/07/2024 02:51:28 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 31/07/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117493 is cancelled at 1420 hrs 28/07/2024

No LOR condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
117498RESERVE NOTICE28/07/2024 02:49:38 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 30/07/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117492 is cancelled at 1420 hrs 28/07/2024

No LOR condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
117497RESERVE NOTICE28/07/2024 12:50:02 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 29/07/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following Period:

[1.] From 0730 hrs 29/07/2024 to 0830 hrs 29/07/2024.
The forecast capacity reserve requirement is 557 MW.
The minimum capacity reserve available is 517 MW.

Manager NEM Real Time Operations
117493RESERVE NOTICE27/07/2024 02:40:49 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 31/07/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117443 has been updated at 1400 hrs 27/07/2024 to the following:

From 0800 hrs 31/07/2024 to 0930 hrs 31/07/2024.
The forecast capacity reserve requirement is 557 MW.
The minimum capacity reserve available is 485 MW.

AEMO Operations