Market Notices

119171RESERVE NOTICE22/10/2024 05:51:39 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 24/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 119166 is cancelled at 0530 hrs 22/10/2024.

No LOR2 condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
     
119166RESERVE NOTICE22/10/2024 01:06:32 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 24/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 119165 has been updated at 0100 hrs 22/10/2024 to the following:

[1.] From 0500 hrs 24/10/2024 to 0630 hrs 24/10/2024.
The forecast capacity reserve requirement is 1437 MW.
The minimum capacity reserve available is 1276 MW.

[2.] From 1700 hrs 24/10/2024 to 2300 hrs 24/10/2024.
The forecast capacity reserve requirement is 1367 MW.
The minimum capacity reserve available is 1251 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
119165RESERVE NOTICE21/10/2024 09:32:53 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 24/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 0500 hrs 24/10/2024 to 0600 hrs 24/10/2024.
The forecast capacity reserve requirement is 1344 MW.
The minimum capacity reserve available is 1297 MW.

[2.] From 1700 hrs 24/10/2024 to 2000 hrs 24/10/2024.
The forecast capacity reserve requirement is 1484 MW.
The minimum capacity reserve available is 1274 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
119141NON-CONFORMANCE21/10/2024 11:05:22 AM

NON-CONFORMANCE Region SA1 Monday, 21 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Monday, 21 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BLYTHB1
Duration: 21/10/2024 10:55 to 21/10/2024 11:05
Amount: 50 MW
Constraint: NC-S_BLYTHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
119140NON-CONFORMANCE21/10/2024 10:25:18 AM

NON-CONFORMANCE Region VIC1 Monday, 21 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Monday, 21 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GLRWNSF1
Duration: 21/10/2024 09:50 to 21/10/2024 10:25
Amount: 62 MW
Constraint: NC-V_GLRWNSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
119036NON-CONFORMANCE18/10/2024 05:10:24 PM

NON-CONFORMANCE Region VIC1 Friday, 18 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Friday, 18 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BRYB2WF2
Duration: 18/10/2024 16:50 to 18/10/2024 17:10
Amount: 10 MW
Constraint: NC-V_BRYB2WF2

Auto-generated on behalf of Manager NEM Real Time Operations
     
119034NON-CONFORMANCE18/10/2024 04:55:17 PM

NON-CONFORMANCE Region SA1 Friday, 18 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Friday, 18 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: HPR1
Duration: 18/10/2024 16:40 to 18/10/2024 16:55
Amount: 22 MW
Constraint: NC-S_HPR1

Auto-generated on behalf of Manager NEM Real Time Operations
     
119020NON-CONFORMANCE18/10/2024 11:25:22 AM

NON-CONFORMANCE Region VIC1 Friday, 18 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Friday, 18 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BULBES1
Duration: 18/10/2024 11:05 to 18/10/2024 11:25
Amount: 20 MW
Constraint: NC-V_BULBES1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118965NON-CONFORMANCE17/10/2024 07:35:25 AM

NON-CONFORMANCE Region VIC1 Thursday, 17 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Thursday, 17 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS4
Duration: 17/10/2024 07:25 to 17/10/2024 07:35
Amount: -53 MW
Constraint: NC-V_YWPS4

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm