STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 20/05/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 116641 has been updated at 1000 hrs 17/05/2024 to the following:
From 0600 hrs 20/05/2024 to 0830 hrs 20/05/2024.
The forecast capacity reserve requirement is 1240 MW.
The minimum capacity reserve available is 868 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 20/05/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 0600 hrs to 0730 hrs 20/05/2024.
The forecast capacity reserve requirement is 1126 MW.
The minimum capacity reserve available is 1121 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Update - Network Augmentation Commissioned - QLD Region - 15/05/2024
Update - Network Augmentation Commissioned - QLD Region - 15/04/2024
Refer Market notice: 115974 and 116446
Guybal Munjan 275 kV Switching Station has been commissioned.
The former Ross - Chalumbin No. 857 and Ross - Chalumbin No. 858 275 kV lines have been replaced with the following lines:
H13 Ross - H93 Guybal Munjan No. 8916 275 kV line
H13 Ross - H93 Guybal Munjan No. 8917 275 kV line
H93 Guybal Munjan - H32 Chalumbin No. 857 275 kV line
H93 Guybal Munjan - H32 Chalumbin No. 858 275 kV line
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/05/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No.116545 is cancelled at 1915 hrs 08/05/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/05/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 09/05/2024 to 1800 hrs 09/05/2024.
The forecast capacity reserve requirement is 862 MW.
The minimum capacity reserve available is 721 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/05/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 116502 is cancelled at 1100 hrs 07/05/2024.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/05/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1700 hrs to 1800 hrs 08/05/2024.
The forecast capacity reserve requirement is 1198 MW.
The minimum capacity reserve available is 973 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Network Augmentation Commissioned - QLD Region - 02/05/2024
Network Augmentation Commissioned - QLD Region - 02/05/2024
Commissioned:
H13 Ross - H93 Guybal Munjan No.8917 275 kV line
Manager NEM Real Time Operations
Planned outage of Gordon - Chapel St No. 1 220 kV line in the TAS region on 26/04/2024
The Gordon - Chapel St No. 1 220 kV line in the Tasmania (TAS) region is planned to be out of service from 1030 hrs on 26/04/2024 to 1500 hrs on 26/04/2024
A credible contingency event during this planned outage could cause a large reduction in generation in TAS.
Refer AEMO Network Outage Schedule (NOS) for further details.
Manager NEM Real Time Operations