121993NON-CONFORMANCE16/12/2024 01:50:14 AM

NON-CONFORMANCE Region QLD1 Monday, 16 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 16 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 16/12/2024 01:10 to 16/12/2024 01:50
Amount: -21 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121941NON-CONFORMANCE15/12/2024 10:55:20 AM

NON-CONFORMANCE Region NSW1 Sunday, 15 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 15 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 15/12/2024 10:45 to 15/12/2024 10:55
Amount: 11 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121940NON-CONFORMANCE15/12/2024 09:10:14 AM

NON-CONFORMANCE Region QLD1 Sunday, 15 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 15 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 15/12/2024 09:00 to 15/12/2024 09:10
Amount: 11 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
121870NON-CONFORMANCE13/12/2024 04:55:23 PM

NON-CONFORMANCE Region QLD1 Friday, 13 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 13 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: KAREEYA1
Duration: 13/12/2024 16:50 to 13/12/2024 16:55
Amount: -21 MW
Constraint: NC-Q_KAREEYA1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121826NON-CONFORMANCE13/12/2024 08:00:15 AM

NON-CONFORMANCE Region VIC1 Friday, 13 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Friday, 13 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BANN1
Duration: 13/12/2024 07:35 to 13/12/2024 08:00
Amount: 71 MW
Constraint: NC-V_BANN1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121806POWER SYSTEM EVENTS12/12/2024 08:52:19 PM

Non-credible contingency event - QLD region - 12/12/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 12/12/2024

At 2026 hrs the Kamerunga to Barron George 132 kV Line 7184 and the Kamerunga to Barron George 132 kV Line 7141 tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
121755NON-CONFORMANCE12/12/2024 05:40:16 AM

NON-CONFORMANCE Region NSW1 Thursday, 12 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 12 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW02
Duration: 12/12/2024 05:35 to 12/12/2024 05:40
Amount: -31 MW
Constraint: NC-N_BW02

Auto-generated on behalf of Manager NEM Real Time Operations
     
121707NON-CONFORMANCE11/12/2024 02:20:15 AM

NON-CONFORMANCE Region QLD1 Wednesday, 11 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 11 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 11/12/2024 02:00 to 11/12/2024 02:20
Amount: -10 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
121703NON-CONFORMANCE10/12/2024 06:25:21 PM

NON-CONFORMANCE Region QLD1 Tuesday, 10 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 10 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 10/12/2024 17:55 to 10/12/2024 18:25
Amount: -18 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm