122109MINIMUM SYSTEM LOAD17/12/2024 03:08:17 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 21/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 21/12/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1705 MW
o MSL2 - 1205 MW
o MSL3 - 705 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:

From 1130 hrs to 1330 hrs 21/12/2024. Minimum regional demand is forecast to be 1643 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO Operations
     
121994NON-CONFORMANCE16/12/2024 03:30:16 AM

NON-CONFORMANCE Region QLD1 Monday, 16 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 16 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 16/12/2024 02:20 to 16/12/2024 03:30
Amount: -18 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121993NON-CONFORMANCE16/12/2024 01:50:14 AM

NON-CONFORMANCE Region QLD1 Monday, 16 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 16 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 16/12/2024 01:10 to 16/12/2024 01:50
Amount: -21 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121941NON-CONFORMANCE15/12/2024 10:55:20 AM

NON-CONFORMANCE Region NSW1 Sunday, 15 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 15 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 15/12/2024 10:45 to 15/12/2024 10:55
Amount: 11 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121940NON-CONFORMANCE15/12/2024 09:10:14 AM

NON-CONFORMANCE Region QLD1 Sunday, 15 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 15 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 15/12/2024 09:00 to 15/12/2024 09:10
Amount: 11 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
121870NON-CONFORMANCE13/12/2024 04:55:23 PM

NON-CONFORMANCE Region QLD1 Friday, 13 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 13 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: KAREEYA1
Duration: 13/12/2024 16:50 to 13/12/2024 16:55
Amount: -21 MW
Constraint: NC-Q_KAREEYA1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121826NON-CONFORMANCE13/12/2024 08:00:15 AM

NON-CONFORMANCE Region VIC1 Friday, 13 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Friday, 13 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BANN1
Duration: 13/12/2024 07:35 to 13/12/2024 08:00
Amount: 71 MW
Constraint: NC-V_BANN1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121755NON-CONFORMANCE12/12/2024 05:40:16 AM

NON-CONFORMANCE Region NSW1 Thursday, 12 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 12 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW02
Duration: 12/12/2024 05:35 to 12/12/2024 05:40
Amount: -31 MW
Constraint: NC-N_BW02

Auto-generated on behalf of Manager NEM Real Time Operations
     
121707NON-CONFORMANCE11/12/2024 02:20:15 AM

NON-CONFORMANCE Region QLD1 Wednesday, 11 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 11 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 11/12/2024 02:00 to 11/12/2024 02:20
Amount: -10 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     