Filter by category
Filter by Date
Declaration of electricity market resumption
Declaration of electricity market resumption
Refer initial AEMO Electricity Market Notice 118149
AEMO declares that the suspension of the spot market in New South Wales, Queensland, South Australia, Tasmania and Victoria will end at 1510 hrs on 05 September 2024.
AEMO has taken sufficient steps to exclude the original event having influence on market processes and AEMO assesses that the possibility of suspending the spot market within the next 24 hours due to the same cause is minimal. AEMO also determines that it can operate the market in accordance with the provisions of the NER.
Relevant Market Notices issued under this suspension: 118149
Manager NEM Real Time Operations
Declaration of electricity market suspension
Declaration of electricity market suspension
AEMO declares the spot market suspended in New South Wales, Queensland, South Australia, Tasmania and Victoria with Market Suspension Schedule Pricing (refer NER clause 3.14.5(b)) from Trading Interval 1355 hrs on 5 September 2024 until further notice.
Dispatch prices for the first one or two dispatch intervals of this market suspension will be reviewed manually.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 1 Leg of Directlink .
The following constraint set was invoked at 0735 hrs 05/09/2024
N-MBTE_1
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Lismore-Lismore132 9W1 132kV Line - NSW region - 02/09/2024
Inter-regional transfer limit variation - Lismore-Lismore132 9W1 132kV Line - NSW region - 02/09/2024
At 1516 hrs 02/09/2024 there was an unplanned outage of Lismore-Lismore132 9W1 132kV Line
The following constraint set(s) invoked at 1525 hrs 02/09/2024
N-LSLS_9U8
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 kV Line - NSW region - 02/09/2024
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 kV Line - NSW region - 02/09/2024
A planned outage of Armidale - Sapphire 8E 330 kV Line in the NSW region was scheduled from 1630 hrs 31/08/2024 to 1800 hrs 02/09/2024.
The outage has been rescheduled for 1630 hrs 31/08/2024 to 1200 hrs 03/09/2024.
The following constraint set(s) invoked at 1630 hrs 31/08/2024
N-ARSR_8E, N-DM_SVC, N-TW_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330kv Line- NSW region - 01/09/2024
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330kv Line - NSW region - 01/09/2024
A planned outage of Armidale - Sapphire 8E 330kv Line in the NSW region was scheduled from 1630 hrs 31/08/2024 to 0910 hrs 02/09/2024.
The outage has been rescheduled for 1630 hrs 31/08/2024 to 1800 hrs 02/09/2024.
The following constraint set(s) invoked at 1630 hrs 31/08/2024
N-ARSR_8E
N-TW_SVC
N-DM_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 kV line - NSW region - 31/08/2024
Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 kV line - NSW region - 31/08/2024
At 1630 hrs 31/08/2024 there was a short notice outage of Armidale - Sapphire 8E 330 kV line.
The following constraint set(s) invoked at 1630 hrs 31/08/2024
N-ARSR_8E, N-TW_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Dumaresq 330 kV SVC - NSW region - 28/08/2024
Inter-regional transfer limit variation - Dumaresq 330 kV SVC - NSW region - 28/08/2024
At 1125 hrs 28/08/2024 there was a short notice outage of Dumaresq 330 kV SVC.
The following constraint set(s) invoked at 1125 hrs 28/08/2024
N-DM_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 28/08/2024
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_SYDS_55E0E615 from 0900 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations