Filter by category
Filter by Date
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 122407
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 24/12/2024.
The direction update is issued at 1630 hrs 23/12/2024.
Manager NEM Real Time Operations
[EventId:202412231545_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 23 December 2024 15:45
Issued by Australian Energy Market Operator Ltd at 1545 hrs on 23 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 23 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1545 hrs on 23 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region QLD1 Monday, 23 December 2024
NON-CONFORMANCE QLD1 Region Monday, 23 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 23/12/2024 09:25 to 23/12/2024 09:40
Amount: 36 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202412221800_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 December 2024 18:00
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 22 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 December 2024.
Refer to market notice: 122412
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1800 hrs on 22 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412221605_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 December 2024 16:05
Issued by Australian Energy Market Operator Ltd at 1605 hrs on 22 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1605 hrs on 22 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 122373
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 24/12/2024.
The direction update is issued at 1600 hrs 22/12/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 122372
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 24/12/2024.
The direction update is issued at 1600 hrs 22/12/2024.
Manager NEM Real Time Operations
[EventId:202412221020_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 December 2024 10:20
Issued by Australian Energy Market Operator Ltd at 1020 hrs on 22 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 December 2024.
Refer to market notice: 122392
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1020 hrs on 22 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412220740_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 December 2024 07:40
Issued by Australian Energy Market Operator Ltd at 0740 hrs on 22 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0740 hrs on 22 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.