Market Notices

122483PRICES UNCHANGED25/12/2024 05:33:10 PM

[EventId:202412251720_confirmed] Prices for interval 25-Dec-2024 17:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 25 December 2024

PRICES ARE NOW CONFIRMED for trading interval 25-Dec-2024 17:20.

In accordance with Market Notice 122478 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
122482PRICES UNCHANGED25/12/2024 05:32:03 PM

[EventId:202412251715_confirmed] Prices for interval 25-Dec-2024 17:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 25 December 2024

PRICES ARE NOW CONFIRMED for trading interval 25-Dec-2024 17:15.

In accordance with Market Notice 122477 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
122481PRICES UNCHANGED25/12/2024 05:30:16 PM

[EventId:202412251710_confirmed] Prices for interval 25-Dec-2024 17:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 25 December 2024

PRICES ARE NOW CONFIRMED for trading interval 25-Dec-2024 17:10.

In accordance with Market Notice 122476 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
122472MARKET INTERVENTION25/12/2024 05:02:24 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 122451


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1700 hrs 25/12/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 2330 hrs 25/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 27/12/2024.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
122470MARKET INTERVENTION25/12/2024 03:56:06 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 122453

Direction is cancelled from: 1600 hrs 25/12/2024

Manager NEM Real Time Operations
     
122468MARKET INTERVENTION25/12/2024 04:59:11 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122459

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 27/12/2024.

The direction update is issued at 1700 hrs 25/12/2024.

Manager NEM Real Time Operations
     
122466MINIMUM SYSTEM LOAD25/12/2024 02:35:51 PM

Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025

AEMO ELECTRICITY MARKET NOTICE
Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 01/01/2025.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1660 MW
- MSL2 - 1160 MW
- MSL3 - 660 MW

The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
- From 1030 hrs 01/01/2025 to 1430 hrs 01/01/2025. Minimum regional demand is forecast to be 1422 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .


Manager NEM Real Time Operations
     
122459MARKET INTERVENTION24/12/2024 04:05:42 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122452

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 26/12/2024.

The direction update is issued at 1605 hrs 24/12/2024.

Manager NEM Real Time Operations
     
122454MINIMUM SYSTEM LOAD24/12/2024 02:49:15 PM

Cancellation of Forecast Minimum System Load MSL1 event in the VIC Region on 29/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Forecast MSL1 - VIC Region at 1400 hrs 24/12/2024.

Refer to Market Notice 122437 for MSL1.

AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm