Filter by category
Filter by Date
Declaration of electricity market suspension
Declaration of electricity market suspension
AEMO declares the spot market suspended in New South Wales, Queensland, South Australia, Tasmania and Victoria with Market Suspension Schedule Pricing (refer NER clause 3.14.5(b)) from Trading Interval 1355 hrs on 5 September 2024 until further notice.
Dispatch prices for the first one or two dispatch intervals of this market suspension will be reviewed manually.
Manager NEM Real Time Operations
Cancellation - Load Restoration Direction in the NSW Region - 08/07/2024
Cancellation - Load Restoration Direction in the NSW Region - 08/07/2024
Refer to AEMO Electricity Market Notice 117322
Load restoration as directed is complete. Direction cancelled from 2200 hrs 08/07/2024
Manager NEM Real Time Operations
Load Restoration Direction in the NSW Region
Load Restoration Direction in the NSW Region
AEMO has directed load restoration commencing at 1930 hrs 08/07/2024
in the NSW region
The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.
Manager NEM Real Time Operations
Load Restoration Direction Cancellation in the Vic Region
Cancellation - Load Restoration Direction in the Vic Region - 13/02/2024
Refer to AEMO Electricity Market Notice ID 114607
Load restoration as directed is complete. Direction cancelled from 1510 hrs 13/02/2024.
Manager NEM Real Time Operations
Load Restoration Direction in the Vic Region
Load Restoration Direction in the Vic Region
AEMO has directed load restoration commencing at 1450 hrs 13/02/2024 in the Victoria region
The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.
Manager NEM Real Time Operations
STPASA - Suspect Lack Of Reserve Level 3 (LOR3) in the QLD Region on 01/02/2024
AEMO considers that there are suspect Forecast LOR3 conditions for the QLD region for the following periods:
1. From 0900 hrs to 1000 hrs 01/02/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 38 MW at 0930 hrs.
2. From 1130 hrs to 1200 hrs 01/02/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 62 MW at 1130 hrs.
AEMO is currently investigating these LOR3 forecast conditions to confirm whether they are valid.
AEMO Operations