118216MARKET SYSTEMS10/09/2024 01:12:57 PM

CHG0098193 | Production | AEMO will be undertaking maintenance activities on the RCM system

Change Number: CHG0098193
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cohesity

Change Title: AEMO will be undertaking maintenance activities on the RCM system
Change Start Date & Time: 11/09/2024 20:00:00 AEST
Change End Date & Time: 12/09/2024 02:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production

Participant Impact and Requirements: AEMO will be undertaking maintenance activities on the NEMSETTLEMENTSR system. Whilst no outage is expected there is potential for transient performance degradation during the change.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
118204RESERVE NOTICE09/09/2024 11:53:31 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118202 is cancelled at 1100 hrs 09/09/2024.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
118202RESERVE NOTICE09/09/2024 11:00:49 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 1830 hrs to 1930 hrs 10/09/2024.
The forecast capacity reserve requirement is 347 MW.
The minimum capacity reserve available is 343 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
118201RESERVE NOTICE09/09/2024 12:36:03 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118200 is cancelled at 0030 hrs 09/09/2024.

No LOR2 condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
118200RESERVE NOTICE08/09/2024 10:34:30 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

[1.] From 1830 hrs 10/09/2024 to 2030 hrs 10/09/2024.
The forecast capacity reserve requirement is 430 MW.
The minimum capacity reserve available is 403 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
118176RESERVE NOTICE07/09/2024 10:42:44 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118175 is cancelled at 2230 hrs 07/09/2024.

No LOR2 condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
118175RESERVE NOTICE07/09/2024 07:48:50 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

[1.] From 1830 hrs 10/09/2024 to 1900 hrs 10/09/2024.
The forecast capacity reserve requirement is 415 MW.
The minimum capacity reserve available is 385 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
118171POWER SYSTEM EVENTS06/09/2024 08:18:58 PM

Update - Non-credible contingency event - VIC region - 06/09/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - VIC region - 06/09/2024

Refer AEMO Electricity Market Notice 118166

At 2005 hrs the Loy Yang PS No. 4 500 kV bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
118166POWER SYSTEM EVENTS06/09/2024 12:38:00 PM

Non-credible contingency event - VIC region - 06/09/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 06/09/2024

At 1222 hrs the Loy Yang PS No. 4 500 kV bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations