Filter by category
Filter by Date
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
[1.] From 1730 hrs 19/05/2024 to 1900 hrs 19/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1331 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 18/05/2024 to 1830 hrs 18/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1281 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116652 is cancelled at 1645 hrs 17/05/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1730 hrs 18/05/2024 to 1800 hrs 18/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1429 MW.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
1. From 0530 hrs to 0600 hrs 20/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1421 MW.
2. From 1600 hrs to 2230 hrs 20/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 807 MW.
AEMO Operations
[EventId:203] AP ENDED for ENERGY in NSW1 at 15 May 2024 03:55
Issued by Australian Energy Market Operator Ltd at 0355 hrs on 14 May 2024
ADMINISTERED PRICE PERIOD ENDS in NSW1 region.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO is notifying market participants that the administered price period declared for the NSW1 region in market notice 116607 will end at 0400 hrs on 15 May 2024.
This is an AEMO autogenerated Market Notice.
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/05/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 116609 is cancelled at 1415 hrs 14/05/2024.
Manager NEM Real Time Operations
[EventId:203] AP STARTED for ENERGY in NSW1 at 14 May 2024 03:55
Issued by Australian Energy Market Operator Ltd at 0355 hrs on 14 May 2024
ADMINISTERED PRICE PERIOD DECLARED in NSW1 region.
AEMO has determined that the rolling sum of the uncapped spot prices for the NSW1 region over the previous 2016 trading intervals has exceeded the cumulative price threshold (CPT) of $1,490,200.00.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO has determined that an administered price period will commence at the trading interval starting 0405 hrs on 14 May 2024 and will continue through to the end of that trading day.
An administered price cap (APC) of 600 $/MWh will apply to all trading intervals during this administered price period. This APC will apply to spot prices and to all market ancillary service prices in the NSW1 region.
An administered floor price (AFP) of -600 $/MWh will apply to spot prices.
AEMO will continue to monitor the rolling sum of the uncapped spot prices and issue further Market Notices as required.
This is an AEMO autogenerated Market Notice.
[EventId:202] AP ENDED for ENERGY in NSW1 at 14 May 2024 03:55
Issued by Australian Energy Market Operator Ltd at 0355 hrs on 13 May 2024
ADMINISTERED PRICE PERIOD ENDS in NSW1 region.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO is notifying market participants that the administered price period declared for the NSW1 region in market notice 116604 will end at 0400 hrs on 14 May 2024.
This is an AEMO autogenerated Market Notice.