[EventId:202408131120_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 August 2024 11:20
Issued by Australian Energy Market Operator Ltd at 1120 hrs on 13 August 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 August 2024.
Refer to market notice: 117661
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1120 hrs on 13 August 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202408131035_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 August 2024 10:35
Issued by Australian Energy Market Operator Ltd at 1035 hrs on 13 August 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 August 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1035 hrs on 13 August 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
CHG0095134 | Completed | Production | AEMO will be undertaking maintenance activities on the SMP system
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the SMP system
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0091753 | Completed | Pre-Production | Pre production Gas Supply Hub (GSH) Environment Outage
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas Supply Hub
Change Title: Pre production Gas Supply Hub (GSH) Environment Outage
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0095132 | Production | AEMO will be undertaking maintenance activities on the DWGM system
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the DWGM system
Change Start Date & Time: 13/08/2024 22:30:42 AEST
Change End Date & Time: 14/08/2024 08:30:42 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements:
AEMO will be undertaking maintenance activities on the DWGM system. Whilst no outage is expected there is potential for transient performance degradation during the change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0095134 | Production | AEMO will be undertaking maintenance activities on the SMP system
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the SMP system
Change Start Date & Time: 11/08/2024 15:00:57 AEST
Change End Date & Time: 12/08/2024 01:00:57 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: AEMO will be undertaking maintenance activities on the SMP system. Whilst no outage is expected there is potential for transient performance degradation during the change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0087952 | Pre-Production | Retail Pre-Production Data refresh (CATS and EMDM)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Retail Pre-Production Data refresh (CATS and EMDM)
Change Start Date & Time: 12/08/2024 09:00:00 AEST
Change End Date & Time: 16/08/2024 18:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Pre-Production
Participant Impact and Requirements: MSATS (preprod), CDR (preprod) and CDP (preprod) will be unavailble between 12th Aug to 16th Aug cob
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
CHG0091753 | Pre-Production | Pre production Gas Supply Hub (GSH) Environment Outage
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Supply Hub
Change Title: Pre production Gas Supply Hub (GSH) Environment Outage
Change Start Date & Time: 08/08/2024 09:00:00 AEST
Change End Date & Time: 09/08/2024 17:00:00 AEST
Outage Start Date & Time: 08/08/2024 09:00:00 AEST
Outage End Date & Time: 09/08/2024 14:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: "The AEMO Pre-production Gas Supply Hub (GSH) environment will be refreshed (GSH databases) and system will be unavailable during the outage window.
Access to Gas Suuply Hub (GSH) Trayport interface, GSH Day Ahead auction (DAA) and Pipeline capacity trading API and GSH web portal interfaces will be unavailable.
Upon completion of the outage users will be required to log in to pre-prod Gas Supply Hub Tray-port application using their production credentials as Trayport passwords in Pre-Production environment will be replaced with their Production passwords."
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
CHG0093394 | Pre-Production | Planned Outage for the Gas Short Term Trading Market Systems SWEXIE Pre-Production.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: STTM - Market Inputs - Manual
Change Title: Planned Outage for the Gas Short Term Trading Market Systems
SWEXIE Pre-Production.
Change Start Date & Time: 06/08/2024 18:30:00 AEST
Change End Date & Time: 06/08/2024 19:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Pre-Production
Participant Impact and Requirements: Gas Short Term Trading Market (STTM) SWEXIE services will not be available during the outage window in Pre-Production.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .