116549RESERVE NOTICE08/05/2024 07:22:48 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No.116545 is cancelled at 1915 hrs 08/05/2024.

Manager NEM Real Time Operations
116545RESERVE NOTICE08/05/2024 05:19:39 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1730 hrs 09/05/2024 to 1800 hrs 09/05/2024.
The forecast capacity reserve requirement is 862 MW.
The minimum capacity reserve available is 721 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
116503RESERVE NOTICE07/05/2024 12:01:42 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 116502 is cancelled at 1100 hrs 07/05/2024.

No LOR2 condition is currently forecast in the STPASA period.


AEMO Operations
116502RESERVE NOTICE07/05/2024 10:02:31 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1700 hrs to 1800 hrs 08/05/2024.
The forecast capacity reserve requirement is 1198 MW.
The minimum capacity reserve available is 973 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations

116446GENERAL NOTICE02/05/2024 07:49:28 PM

Network Augmentation Commissioned - QLD Region - 02/05/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 02/05/2024

Commissioned:

H13 Ross - H93 Guybal Munjan No.8917 275 kV line

Manager NEM Real Time Operations
116339POWER SYSTEM EVENTS26/04/2024 12:12:59 PM

Non-credible contingency event - NSW region - 26/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 26/04/2024

At 1112 hrs the Griffith to Darlington Point 132kV line (99K) and the Darlington Point BESS disconnected.

AEMO did not instruct load shedding.

AEMO observed 5 MW of electrical load lost.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
116329GENERAL NOTICE25/04/2024 11:56:40 AM

Planned outage of Gordon - Chapel St No. 1 220 kV line in the TAS region on 26/04/2024

AEMO ELECTRICITY MARKET NOTICE

The Gordon - Chapel St No. 1 220 kV line in the Tasmania (TAS) region is planned to be out of service from 1030 hrs on 26/04/2024 to 1500 hrs on 26/04/2024

A credible contingency event during this planned outage could cause a large reduction in generation in TAS.

Refer AEMO Network Outage Schedule (NOS) for further details.

Manager NEM Real Time Operations
116299POWER SYSTEM EVENTS24/04/2024 10:54:59 AM

Non-credible contingency event - QLD region - 24/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 24/04/2024

At 0855 hrs the Ross - Guybal Munjan 8916 275 kV line tripped at the Guybal Munjan end only.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.


Manager NEM Real Time Operations
116276POWER SYSTEM EVENTS23/04/2024 12:09:41 PM

Non-credible contingency event - VIC region - 23/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 23/04/2024

At 1056 hrs the MOPS 11 Gen TX 2 Bus 500kV CB and the Dundonnell WF tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.


Manager NEM Real Time Operations