Market Notices

116567RESERVE NOTICE09/05/2024 07:15:54 PM

Cancellation of Actual (LOR1) condition in the NSW region - 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 09/05/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.116566 is cancelled at 1915 hrs 09/05/2024.

Manager NEM Real Time Operations
116566RESERVE NOTICE09/05/2024 05:13:13 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/05/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs.

The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 964 MW

Manager NEM Real Time Operations
116549RESERVE NOTICE08/05/2024 07:22:48 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No.116545 is cancelled at 1915 hrs 08/05/2024.

Manager NEM Real Time Operations
116548RESERVE NOTICE08/05/2024 07:11:28 PM

Cancellation of Actual (LOR1) condition in the NSW region - 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 08/05/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.116547 is cancelled at 1915 hrs 08/05/2024.

Manager NEM Real Time Operations
116547RESERVE NOTICE08/05/2024 05:45:01 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/05/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs.

The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 1417 MW

Manager NEM Real Time Operations
116545RESERVE NOTICE08/05/2024 05:19:39 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1730 hrs 09/05/2024 to 1800 hrs 09/05/2024.
The forecast capacity reserve requirement is 862 MW.
The minimum capacity reserve available is 721 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
116514RESERVE NOTICE07/05/2024 07:17:19 PM

Cancellation of Actual (LOR1) condition in the NSW region - 07/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 07/05/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No. 116513 is cancelled at 1915 hrs 07/05/2024.

Manager NEM Real Time Operations
116513RESERVE NOTICE07/05/2024 05:46:36 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/05/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 1366 MW

Manager NEM Real Time Operations
116503RESERVE NOTICE07/05/2024 12:01:42 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 116502 is cancelled at 1100 hrs 07/05/2024.

No LOR2 condition is currently forecast in the STPASA period.


AEMO Operations