[EventId:202409301435_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 30 September 2024 14:35
Issued by Australian Energy Market Operator Ltd at 1435 hrs on 30 September 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 September 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1435 hrs on 30 September 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Heywood testing (SA to Vic) 30th September 2024
There is an opportunity for testing Heywood Interconnector (HIC) flow from South Australia to Victoria above 450MW and Victoria to South Australia above 450MW on 30th September from 9:00hrs to 17:00hrs
This test includes a trip and reclose of a line in South Australia.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Ben Blake
AEMO Operations
[EventId:202409291900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 September 2024 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 29 September 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 September 2024.
Refer to market notice: 118524
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 29 September 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202409291820_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 September 2024 18:20
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 29 September 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 September 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1820 hrs on 29 September 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Network Augmentation Commissioned - NSW Region - 27/09/2024
A network augmentation has been commissioned in the NSW region at 2150 hrs 27/09/2024 as follows:
Walla Walla substation has been cut into the existing Wagga - Jinderra (62) 330 kV line to form the following circuits:
Jinderra - Walla Walla 62 330 kV Transmission Line
Walla Walla - Wagga 6Y 330 kV Transmission Line
Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 24/09/2024
Network Augmentation Commissioned - NSW Region - 24/09/2024
At 1535 hrs Buronga - Redcliffs X1 220 kV line has been commissioned.
Manager NEM Real Time Operations
Update - Lightning vulnerable lines in TAS region
Update - Lightning vulnerable lines in TAS region
Refer to AEMO Electricity Market Notice 118320 ,118321, 118322
At 1340 hrs 19/09/2024 the Gordon - Chapel St No 1 220 kV line and the Gordon - Chapel St No 2 220 kV line tripped.
The cause of the trip was identified as due to Lightning.
In accordance with SO_OP_3715, AEMO now considers the Gordon - Chapel St No 1 220 kV line and the Gordon - Chapel St No 2 220 kV line to be vulnerable with a category of Vulnerability due to Lightning.
Manager NEM Real Time Operations
Update - Non-credible contingency event - TAS region - 19/09/2024
Update - Non-credible contingency event - TAS region - 19/09/2024
Refer AEMO Electricity Market Notice 118321
At 1446 hrs the Gordon - Chapel St No 1 and No 2 220 kV lines were returned to service.
This non-credible contingency event was caused by lightning. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Manager NEM Real Time Operations
Update - Non-credible contingency event - TAS region - 19/09/2024
Update - Non-credible contingency event - TAS region - 19/09/2024
At 1340 hrs the Gordon - Chapel St No1 and No 2 220 kV lines tripped.
AEMO did not instruct load shedding.
AEMO has advised of approximately 112 MW disconnection of bulk electrical load,
disconnection of generation at Studland Bay Wind generator (71 MW) and 23 MW generation reduction at Gordon Power station.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations