INC0126874 | Overnight standing data updates not reflecting in MSATS Enterprise MDM
SERVICE INTERRUPTION - ALERT
AEMO is experiencing a service interruption relating to the Market Settlement & Transfer Solution Enterprise MDM service.
The overnight MSATS CATS change requests are not reflected in the MSATS Enterprise MDM. This has also impacted the Meter Data ingestion.
MDPs are advised to not resend meter data files until advised or resolved notification for this incident has been received.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
NON-CONFORMANCE Region SA1 Tuesday, 13 February 2024
NON-CONFORMANCE SA1 Region Tuesday, 13 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TORRB4
Duration: 13/02/2024 17:45 to 13/02/2024 17:50
Amount: 14 MW
Constraint: NC-S_TORRB4
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Tuesday, 13 February 2024
NON-CONFORMANCE SA1 Region Tuesday, 13 February 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: HPRG1, HPRL1
Aggregate Dispatch Group: HORNSDPR_ADG1
Duration: 13/02/2024 17:45 to 13/02/2024 17:50
Amount: 20 MW
Constraint: NC-S_HORNSDPR_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR2) condition in the VIC region - 13/02/2024
Cancellation of Actual (LOR2) condition in the VIC region - 13/02/2024
The Actual LOR2 Condition in the VIC Region advised in AEMO Electricity Market Notice No.114589 is cancelled at 1614 hrs 13/02/2024.
Manager NEM Real Time Operations
Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024
Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024
The Actual LOR3 Condition in the VIC region advised in AEMO Electricity Market Notice No.114604 is cancelled at 1515 hrs 13/02/2024.
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Tuesday, 13 February 2024
NON-CONFORMANCE VIC1 Region Tuesday, 13 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS4
Duration: 13/02/2024 14:50 to 13/02/2024 14:55
Amount: -25 MW
Constraint: NC-V_YWPS4
Auto-generated on behalf of Manager NEM Real Time Operations
Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024
Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024
Customer load shedding of non-interruptible load is occurring in the VIC region as a result of a shortfall of available capacity reserves.
An Actual LOR3 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the VIC region from 1420 hrs.
The Actual LOR3 condition is not forecast in Pre Dispatch.
The maximum load to be interrupted is up to 450 MW from 1420 hrs 13/02/2024
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 13 February 2024
NON-CONFORMANCE QLD1 Region Tuesday, 13 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 13/02/2024 12:05 to 13/02/2024 12:10
Amount: 15 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 13 February 2024
NON-CONFORMANCE QLD1 Region Tuesday, 13 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 13/02/2024 11:10 to 13/02/2024 11:25
Amount: 10 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations