Market Notices

118382RESERVE NOTICE22/09/2024 10:30:45 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1930 hrs 23/09/2024 to 2000 hrs 23/09/2024.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 322 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
118373RESERVE NOTICE22/09/2024 04:15:36 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118363 is cancelled at 16:15 hrs 22/09/2024.

Manager NEM Real Time Operations
118363RESERVE NOTICE22/09/2024 12:54:20 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1830 hrs 23/09/2024 to 2030 hrs 23/09/2024.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 260 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
118362RESERVE NOTICE22/09/2024 03:02:38 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118361 is cancelled at 0300 hrs 22/09/2024.

No LOR2 condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
118361RESERVE NOTICE21/09/2024 10:35:00 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

[1.] From 1430 hrs 24/09/2024 to 1600 hrs 24/09/2024.
The forecast capacity reserve requirement is 516 MW.
The minimum capacity reserve available is 462 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
118360NON-CONFORMANCE21/09/2024 07:20:17 PM

NON-CONFORMANCE Region NSW1 Saturday, 21 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 21 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 21/09/2024 15:00 to 21/09/2024 19:20
Amount: 7 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
118355NON-CONFORMANCE21/09/2024 11:35:22 AM

NON-CONFORMANCE Region QLD1 Saturday, 21 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 21 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MOUSF1
Duration: 21/09/2024 10:55 to 21/09/2024 11:35
Amount: 81 MW
Constraint: NC-Q_MOUSF1

Auto-generated on behalf of Manager NEM Real Time Operations
118346NON-CONFORMANCE20/09/2024 06:25:11 PM

NON-CONFORMANCE Region QLD1 Friday, 20 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 20 September 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: WDBESSG1, WDBESSL1
Aggregate Dispatch Group: WDBESS_ADG1
Duration: 20/09/2024 18:10 to 20/09/2024 18:25
Amount: -63 MW
Constraint: NC-Q_WDBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
118343NON-CONFORMANCE20/09/2024 05:40:18 PM

NON-CONFORMANCE Region QLD1 Friday, 20 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 20 September 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: WDBESSG1, WDBESSL1
Aggregate Dispatch Group: WDBESS_ADG1
Duration: 20/09/2024 17:15 to 20/09/2024 17:40
Amount: -63 MW
Constraint: NC-Q_WDBESS_ADG1