Filter by category
Filter by Date
Update to system normal constraint equation in NSW for transient voltage stability in south-west NSW
Refer to market notice 92840.
Transgrid has advised AEMO of an update to the transient voltage stability limit in south-west NSW for loss of Darlington Point to Wagga (63) 330 kV line. The limit will include terms for the Darlington Point and Riverina BESS.
The following constraint equation will be updated with the above changes at 1100 hrs Friday 20th September 2024.
N::N_NIL_63
For full details on the formulation, the new constraint equation has now been loaded into AEMO's pre-production systems.
For further details on these constraint equation please contact ben.blake@aemo.com.au
Ben Blake
AEMO Operations
NON-CONFORMANCE Region SA1 Wednesday, 18 September 2024
NON-CONFORMANCE SA1 Region Wednesday, 18 September 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 18/09/2024 11:20 to 18/09/2024 12:50
Amount: 21 MW
Constraint: NC-S_TB2HYB_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Tuesday, 17 September 2024
NON-CONFORMANCE SA1 Region Tuesday, 17 September 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MANNSF2
Duration: 17/09/2024 14:10 to 17/09/2024 15:00
Amount: 23 MW
Constraint: NC-S_MANNSF2
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202409121655_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 12 September 2024 16:55
Issued by Australian Energy Market Operator Ltd at 1655 hrs on 12 September 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 September 2024.
Refer to market notice: 118256
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1655 hrs on 12 September 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202409121505_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 12 September 2024 15:05
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 12 September 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 September 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1505 hrs on 12 September 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202409121130_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 12 September 2024 11:30
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 12 September 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 September 2024.
Refer to market notice: 118247
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1130 hrs on 12 September 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202409121035_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 12 September 2024 10:35
Issued by Australian Energy Market Operator Ltd at 1035 hrs on 12 September 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 September 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1035 hrs on 12 September 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region QLD1 Tuesday, 10 September 2024
NON-CONFORMANCE QLD1 Region Tuesday, 10 September 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 10/09/2024 03:50 to 10/09/2024 04:10
Amount: 39 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 9 September 2024
NON-CONFORMANCE QLD1 Region Monday, 9 September 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 09/09/2024 17:25 to 09/09/2024 17:40
Amount: -32 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations