Market Notices

118645MINIMUM SYSTEM LOAD07/10/2024 02:49:02 PM

STPASA - Forecast Minimum System Load 1 (MSL1) in the VIC Region on 13/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1100 hrs 13/10/2024 to 1400 hrs 13/10/2024.

Minimum regional demand is forecast to be 1623 MW at 1300 hrs, and the advisory threshold is:

o MSL1 - 1865 MW
o MSL2 - 1365 MW
o MSL3 - 865 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.

AEMO Operations
     
118493MINIMUM SYSTEM LOAD28/09/2024 02:30:26 PM

Cancellation - MSL1- VIC Region at 1430 hrs 28/09/2024.

AEMO ELECTRICITY MARKET NOTICE

Cancellation - MSL1- VIC Region at 1430 hrs 28/09/2024.
Refer to Market Notice 118475.

Manager NEM Real Time Operations
     
118483MINIMUM SYSTEM LOAD27/09/2024 03:35:11 PM

Cancellation - MSL1- VIC Region at 1530 hrs 27/09/2024.

AEMO ELECTRICITY MARKET NOTICE
Cancellation - MSL1- VIC Region at 1530 hrs 27/09/2024.
Refer to Market Notice 118442 for MSL1.
Manager NEM Real Time Operations
     
118475MINIMUM SYSTEM LOAD27/09/2024 10:55:57 AM

Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024

AEMO ELECTRICITY MARKET NOTICE

Update to Market Notice 118421.

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1030 hrs to 1430 hrs 28/09/2024.

Minimum regional demand is forecast to be 1420 MW at 1200 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.

Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem

AEMO is seeking a market response.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in action such as the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.

AEMO Operations
     
118442MINIMUM SYSTEM LOAD25/09/2024 03:14:36 PM

Minimum System Load 1 (MSL1) in the VIC Region on 27/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1300 hrs 27/09/2024 to 1330 hrs 27/09/2024.

Minimum regional demand is forecast to be 1879 MW at 1330 hrs, and the advisory threshold is:
o MSL1 - 1915 MW
o MSL2 - 1415 MW
o MSL3 - 915 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.

Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem

AEMO is seeking a market response.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in action such as the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.

AEMO Operations
     
118421MINIMUM SYSTEM LOAD24/09/2024 02:54:54 PM

Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1100 hrs to 1400 hrs 28/09/2024.
Minimum regional demand is forecast to be 1638 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.

Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem

AEMO is seeking a market response.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in actions such as recalling network outages, the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.

AEMO Operations
     
118150MARKET SUSPENSION05/09/2024 02:41:01 PM

Declaration of electricity market resumption

AEMO ELECTRICITY MARKET NOTICE

Declaration of electricity market resumption

Refer initial AEMO Electricity Market Notice 118149

AEMO declares that the suspension of the spot market in New South Wales, Queensland, South Australia, Tasmania and Victoria will end at 1510 hrs on 05 September 2024.

AEMO has taken sufficient steps to exclude the original event having influence on market processes and AEMO assesses that the possibility of suspending the spot market within the next 24 hours due to the same cause is minimal. AEMO also determines that it can operate the market in accordance with the provisions of the NER.

Relevant Market Notices issued under this suspension: 118149

Manager NEM Real Time Operations
     
118149MARKET SUSPENSION05/09/2024 02:31:20 PM

Declaration of electricity market suspension

AEMO ELECTRICITY MARKET NOTICE

Declaration of electricity market suspension

AEMO declares the spot market suspended in New South Wales, Queensland, South Australia, Tasmania and Victoria with Market Suspension Schedule Pricing (refer NER clause 3.14.5(b)) from Trading Interval 1355 hrs on 5 September 2024 until further notice.

Dispatch prices for the first one or two dispatch intervals of this market suspension will be reviewed manually.

Manager NEM Real Time Operations
     
117324LOAD RESTORE08/07/2024 09:58:40 PM

Cancellation - Load Restoration Direction in the NSW Region - 08/07/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Load Restoration Direction in the NSW Region - 08/07/2024

Refer to AEMO Electricity Market Notice 117322
Load restoration as directed is complete. Direction cancelled from 2200 hrs 08/07/2024

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm