Cancellation of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV
Cancellation time: 26/12/2024 17:43
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 122495
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Thursday, 26 December 2024
NON-CONFORMANCE VIC1 Region Thursday, 26 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LYA4
Duration: 26/12/2024 16:00 to 26/12/2024 16:20
Amount: -13 MW
Constraint: NC-V_LYA4
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV
Duration: 26/12/2024 16:11 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV
Duration: 26/12/2024 16:11 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Thursday, 26 December 2024
NON-CONFORMANCE SA1 Region Thursday, 26 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: HPR1
Duration: 26/12/2024 15:50 to 26/12/2024 15:55
Amount: 14 MW
Constraint: NC-S_HPR1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Thursday, 26 December 2024
NON-CONFORMANCE SA1 Region Thursday, 26 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TBSF1
Duration: 26/12/2024 09:35 to 26/12/2024 13:10
Amount: 17 MW
Constraint: NC-S_TBSF1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202412251705_confirmed] Prices for interval 25-Dec-2024 17:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 25 December 2024
PRICES ARE NOW CONFIRMED for trading interval 25-Dec-2024 17:05.
In accordance with Market Notice 122475 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412251730_confirmed] Prices for interval 25-Dec-2024 17:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 25 December 2024
PRICES ARE NOW CONFIRMED for trading interval 25-Dec-2024 17:30.
In accordance with Market Notice 122480 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412251725_confirmed] Prices for interval 25-Dec-2024 17:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 25 December 2024
PRICES ARE NOW CONFIRMED for trading interval 25-Dec-2024 17:25.
In accordance with Market Notice 122479 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.