Market Notices

114131NON-CONFORMANCE01/02/2024 06:40:12 PM

NON-CONFORMANCE Region QLD1 Thursday, 1 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 1 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 01/02/2024 18:30 to 01/02/2024 18:40
Amount: 50 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
114114NON-CONFORMANCE01/02/2024 01:45:21 PM

NON-CONFORMANCE Region QLD1 Thursday, 1 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 1 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 01/02/2024 12:25 to 01/02/2024 13:45
Amount: -44 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
114059NON-CONFORMANCE31/01/2024 09:45:16 AM

NON-CONFORMANCE Region QLD1 Wednesday, 31 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 31 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 31/01/2024 09:35 to 31/01/2024 09:45
Amount: 40 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
114056MARKET SYSTEMS31/01/2024 08:43:18 AM

CHG0082222 | Completed | Production | EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Number: CHG0082222

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Electricity Market Management System

Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
114012MARKET SYSTEMS30/01/2024 01:47:21 PM

CHG0082787 | Completed | Pre-Production | Pre-Production MSATS r50.0.5 Patch Release

Change Number: CHG0082787

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)

Change Title: Pre-Production MSATS r50.0.5 Patch Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
113983NON-CONFORMANCE29/01/2024 04:05:13 PM

NON-CONFORMANCE Region NSW1 Monday, 29 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 29 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TALWA1
Duration: 29/01/2024 16:00 to 29/01/2024 16:05
Amount: 66 MW
Constraint: NC-N_TALWA1

Auto-generated on behalf of Manager NEM Real Time Operations
113954NON-CONFORMANCE28/01/2024 10:05:15 PM

NON-CONFORMANCE Region SA1 Sunday, 28 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Sunday, 28 January 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: HPRG1, HPRL1
Aggregate Dispatch Group: HORNSDPR_ADG1
Duration: 28/01/2024 21:55 to 28/01/2024 22:05
Amount: 38 MW
Constraint: NC-S_HORNSDPR_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
113826NON-CONFORMANCE27/01/2024 03:25:10 AM

NON-CONFORMANCE Region SA1 Saturday, 27 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Saturday, 27 January 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: HPRG1, HPRL1
Aggregate Dispatch Group: HORNSDPR_ADG1
Duration: 27/01/2024 03:20 to 27/01/2024 03:25
Amount: 15 MW
Constraint: NC-S_HORNSDPR_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
113763NON-CONFORMANCE26/01/2024 08:15:19 AM

NON-CONFORMANCE Region QLD1 Friday, 26 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 26 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 26/01/2024 08:05 to 26/01/2024 08:15
Amount: -39 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations