Filter by category
Filter by Date
NON-CONFORMANCE Region QLD1 Thursday, 1 February 2024
NON-CONFORMANCE QLD1 Region Thursday, 1 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 01/02/2024 18:30 to 01/02/2024 18:40
Amount: 50 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 1 February 2024
NON-CONFORMANCE QLD1 Region Thursday, 1 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 01/02/2024 12:25 to 01/02/2024 13:45
Amount: -44 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 31 January 2024
NON-CONFORMANCE QLD1 Region Wednesday, 31 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 31/01/2024 09:35 to 31/01/2024 09:45
Amount: 40 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0082222 | Completed | Production | EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Electricity Market Management System
Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0082787 | Completed | Pre-Production | Pre-Production MSATS r50.0.5 Patch Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Production MSATS r50.0.5 Patch Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
NON-CONFORMANCE Region NSW1 Monday, 29 January 2024
NON-CONFORMANCE NSW1 Region Monday, 29 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TALWA1
Duration: 29/01/2024 16:00 to 29/01/2024 16:05
Amount: 66 MW
Constraint: NC-N_TALWA1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Sunday, 28 January 2024
NON-CONFORMANCE SA1 Region Sunday, 28 January 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: HPRG1, HPRL1
Aggregate Dispatch Group: HORNSDPR_ADG1
Duration: 28/01/2024 21:55 to 28/01/2024 22:05
Amount: 38 MW
Constraint: NC-S_HORNSDPR_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Saturday, 27 January 2024
NON-CONFORMANCE SA1 Region Saturday, 27 January 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: HPRG1, HPRL1
Aggregate Dispatch Group: HORNSDPR_ADG1
Duration: 27/01/2024 03:20 to 27/01/2024 03:25
Amount: 15 MW
Constraint: NC-S_HORNSDPR_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 26 January 2024
NON-CONFORMANCE QLD1 Region Friday, 26 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 26/01/2024 08:05 to 26/01/2024 08:15
Amount: -39 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations