Filter by category
Filter by Date
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 01/07/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117201 is cancelled at 1400 hrs 27/06/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
CHG0090782 | Completed | Production | Planned Outage for the Gas Short Term Trading Market Systems Production.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Non-credible contingency event - NSW region - 27/06/2024
Non-credible contingency event - NSW region - 27/06/2024
At 0845 hrs the Sydney West No.1 330 kV SVC tripped during switching for planned outage of Sydney West No.4 330/132 kV transformer.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
CHG0090805 | Completed | Production | Identity Service Site Transfer
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Identity Service (IDS)
Change Title: Identity Service Site Transfer
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
1. From 0800 hrs to 0900 hrs 03/07/2024.
The forecast capacity reserve requirement is 532 MW.
The minimum capacity reserve available is 505 MW.
2. From 1730 hrs to 2030 hrs 03/07/2024.
The forecast capacity reserve requirement is 526 MW.
The minimum capacity reserve available is 496 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 02/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
1. From 0800 hrs to 0900 hrs 02/07/2024.
The forecast capacity reserve requirement is 536 MW.
The minimum capacity reserve available is 454 MW.
2. From 1730 hrs to 2130 hrs 02/07/2024.
The forecast capacity reserve requirement is 546 MW.
The minimum capacity reserve available is 414 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 01/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 1800 hrs to 2130 hrs 01/07/2024.
The forecast capacity reserve requirement is 514 MW.
The minimum capacity reserve available is 467 MW.
AEMO Operations
CHG0090725 | Completed | Pre-Production | Pre-Prod MSATS and eMDM July Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS and eMDM July Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0090802 | Completed | Production | EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Electricity Market Management System
Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.