Filter by category
Filter by Date
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region beginning on 08/09/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 118179 is cancelled at 1320 hrs 08/09/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/09/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1830 hrs 09/09/2024 to 0400 hrs 10/09/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 442 MW.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 10/09/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
[1.] From 1830 hrs 10/09/2024 to 2230 hrs 10/09/2024.
The forecast capacity reserve requirement is 460 MW.
The minimum capacity reserve available is 376 MW.
Manager NEM Real Time Operations
Update - Non-credible contingency event - VIC region - 06/09/2024
Update - Non-credible contingency event - VIC region - 06/09/2024
Refer AEMO Electricity Market Notice 118166
At 2005 hrs the Loy Yang PS No. 4 500 kV bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - VIC region - 06/09/2024
Non-credible contingency event - VIC region - 06/09/2024
At 1222 hrs the Loy Yang PS No. 4 500 kV bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
CHG0098106 | Completed | Production | EMMS Production Bay transfer
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Electricity Market Management System
Change Title: EMMS Production Bay transfer
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0097007 | Cancelled | Production | AEMO will be undertaking maintenance activities on the NEMSETTLEMENTSR system.
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the NEMSETTLEMENTSR system.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0097010 | Cancelled | Production | AEMO will be undertaking maintenance activities on the RCM system
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the RCM system
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0097011 | Cancelled | Production | AEMO will be undertaking maintenance activities on the EMMS - MATRIXIDR,Stpasa system
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the EMMS - MATRIXIDR,Stpasa system
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600