STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 19/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1500 hrs 19/01/2024 to 1600 hrs 19/01/2024.
The forecast capacity reserve requirement is 708 MW.
The minimum capacity reserve available is 671 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 18/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113285 is cancelled at 0700 hrs 16/01/2024.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 18/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1730 hrs 18/01/2024 to 2030 hrs 18/01/2024.
The forecast capacity reserve requirement is 870 MW.
The minimum capacity reserve available is 681 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - South East CB6611 - SA region - 11/01/2024
Inter-regional transfer limit variation - South East CB6611 - SA region - 11/01/2024
At 0955 hrs 11/01/2024 there was an short notice outage of South East CB6611.
The following constraint set(s) invoked at 0955 hrs 11/01/2024
S-SECB6611_10
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Crowlands-Bulgana-Horsham 220 kV Line - Vic region - 07/01/2024
Inter-regional transfer limit variation - Crowlands-Bulgana-Horsham 220 kV Line - Vic region - 07/01/2024
At 1152 hrs 07/01/2024 there was an unplanned outage of the Crowlands-Bulgana-Horsham 220 kV Line.
The following constraint set invoked at 12:05 hrs 07/01/2024
V-CWHO
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
V-SA
VIC1-NSW1
T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - South Pine SVC - QLD region - 03/01/2024
Inter-regional transfer limit variation - South Pine SVC - QLD region - 03/01/2024
At 1220 hrs 03/01/2024 there was an unplanned outage of the South Pine SVC.
The following constraint set(s) invoked at 1230 hrs 03/01/2024
Q-SP_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).
Refer AEMO Electricity Market Notice 113007
AEMO has been notified that the controls to vary Directlink output are now available.
Constraint set I-CTRL_ISSUE_TE revoked at 0940 hrs.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.
Constraint set I-CTRL_ISSUE_TE invoked from 0920 hrs.
The constraint set contains equations with the following interconnector on the LHS:
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 1 Leg of Directlink .
The following constraint set was invoked at 0845 hrs 03/01/2024
N-X_MBTE_2
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.