CHG0089794 | Cancelled | Production | EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: EMMS Production Systems will be transferred to the alternative datacentre for maintenance activities .
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0090550 | Cancelled | Production | Maintenance activities to be performed on the Gas Short Term Trading Market Systems Production.
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Gas FRC - CATS
Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Production.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 18/06/2024 to 2030 hrs 18/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1148 MW.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 21/06/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 0000 hrs to 0030 hrs 21/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1677 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117025 has been updated at 1400 hrs 17/06/2024 to the following:
1. From 0000 hrs to 0100 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1669 MW.
2. From 0600 hrs to 1000 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1651 MW.
3. From 1600 hrs to 2359 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1641 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117024 has been updated at 1400 hrs 17/06/2024 to the following:
1. From 0600 hrs to 0900 hrs 19/06/2024.
The forecast capacity reserve requirement is 1692 MW.
The minimum capacity reserve available is 1565 MW.
2. From 1600 hrs to 2359 hrs 19/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1556 MW.
AEMO Operations
CHG0089836 | Completed | Pre-Production | Renewal and update of AEMO's FBS-Test-Hub.aemo.com.au server certificate.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas Hub
Change Title: Renewal and update of AEMO's FBS-Test-Hub.aemo.com.au server certificate.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117019 has been updated at 1400 hrs 16/06/2024 to the following:
[2.] From 1600 hrs 19/06/2024 to 0030 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1535 MW.
.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117018 has been updated at 1400 hrs 16/06/2024 to the following:
[1.] From 0530 hrs 19/06/2024 to 0930 hrs 19/06/2024.
The forecast capacity reserve requirement is 1721 MW.
The minimum capacity reserve available is 1521 MW.
[2.] From 1600 hrs 19/06/2024 to 0030 hrs 20/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1535 MW.
Manager NEM Real Time Operations