Filter by category
Filter by Date
Forecast Minimum System Load (MSL1) condition in the VIC region on 03/11/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 03/11/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1770 MW
o MSL2 - 1270 MW
o MSL3 - 770 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1100 hrs to 1400 hrs 03/11/2024. Minimum regional demand is forecast to be 1424 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
Manager NEM Real Time Operations
Cancellation - Forecast Minimum System Load MSL1 condition in the VIC Region on 02/11/2024
Cancellation - Forecast Minimum System Load MSL1 condition in the VIC Region at 1200 hrs 02/11/2024.
Refer to Market Notice 119742.
Manager NEM Real Time Operations
Actual Minimum System Load MSL1 condition in the VIC Region on 03/11/2024
Actual Minimum System Load MSL1 condition in the VIC Region on 03/11/2024
Update to Market Notice 119811 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 03/11/2024.
Minimum regional demand is forecast to be 1623 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1770 MW
- MSL2 - 1270 MW
- MSL3 - 770 MW
The regional demand is below the MSL1 threshold. The actual MSL1 condition is forecast to exist until 1400 hrs.
Manager NEM Real Time Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 05/11/2024
Update to Market Notice 119682 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 05/11/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1535 MW
o MSL2 - 1035 MW
o MSL3 - 535 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1000 hrs to 1430 hrs 05/11/2024. Minimum regional demand is forecast to be 1106 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 02/11/2024
Update to Market Notice 119644 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 02/11/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1685 MW
o MSL2 - 1185 MW
o MSL3 - 685 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1030 hrs to 1400 hrs 02/11/2024. Minimum regional demand is forecast to be 1304 MW at 1230 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 03/11/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 03/11/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1795 MW
o MSL2 - 1295 MW
o MSL3 - 795 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1330 hrs 03/11/2024. Minimum regional demand is forecast to be 1684 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
Network Augmentation Commissioned - NSW Region - 31/10/2024
Network Augmentation Commissioned - NSW Region - 31/10/2024
At 1200 hrs 31/10/2024, the Buronga No.4 330kV synchronous condenser has been commissioned.
Manager NEM Real Time Operations
Fast Frequency Response Market - Increase in R1 FCAS dispatch caps from 4th November 2024
Following review of the operation of the Very Fast FCAS market, from 1300 hrs AEST on Monday 4th November AEMO will increase the cap on dispatch of Very Fast Raise (R1) Contingency FCAS from 350 MW to 375 MW
No other changes to the dispatch of Very Fast FCAS or FCAS constraint equation changes will be made on this date.
For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response
Andrew Groom
AEMO Operations
Inter-regional transfer limit variation - Wagga B 330 kV Bus - NSW region - 31/10/2024
Inter-regional transfer limit variation - Wagga B 330 kV bus- NSW region - 31/10/2024
At 0028 hrs 31/10/2024 there was an unplanned outage of Wagga B 330 kV bus.
The following constraint set(s) invoked at 0045 hrs 31/10/2024
N-WAGGA_330_BUSB, N-JNWG_RADIAL, V-DBUSS_L and V-DBUSS_T
This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations