Market Notices

122070RESERVE NOTICE17/12/2024 12:59:30 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122005 has been updated to the following:

[1.] From 1530 hrs 17/12/2024 to 1800 hrs 17/12/2024.
The forecast capacity reserve requirement is 914 MW.
The minimum capacity reserve available is 553 MW.

AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
122050SETTLEMENTS RESIDUE16/12/2024 07:00:24 PM

[EventId:202412161900_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 16 December 2024 19:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 16 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 December 2024.

Refer to market notice: 122046

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1900 hrs on 16 December 2024.

This is an AEMO autogenerated Market Notice.
     
122049RESERVE NOTICE16/12/2024 06:40:21 PM

Cancellation of Actual (LOR1) condition in the NSW region - 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 16/12/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.122029 is cancelled at 1835 hrs 16/12/2024.

Manager NEM Real Time Operations
     
122046SETTLEMENTS RESIDUE16/12/2024 06:00:24 PM

[EventId:202412161800_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 16 December 2024 18:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 16 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1800 hrs on 16 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
122029RESERVE NOTICE16/12/2024 05:21:43 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/12/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 1340 MW
The minimum capacity reserve available is 1297 MW

Manager NEM Real Time Operations
     
122025SETTLEMENTS RESIDUE16/12/2024 05:02:11 PM

[EventId:202412161700_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 16 December 2024 17:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 16 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 December 2024.

Refer to market notice: 122016

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1700 hrs on 16 December 2024.

This is an AEMO autogenerated Market Notice.
     
122016SETTLEMENTS RESIDUE16/12/2024 03:30:25 PM

[EventId:202412161530_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 16 December 2024 15:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1530 hrs on 16 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1530 hrs on 16 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
122009RESERVE NOTICE16/12/2024 01:35:21 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122002 is cancelled at 1330 hrs 16/12/2024.

Manager NEM Real Time Operations
     
122007RESERVE NOTICE16/12/2024 01:11:27 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

From 1830 hrs 17/12/2024 to 1900 hrs 17/12/2024.
The forecast capacity reserve requirement is 1542 MW.
The minimum capacity reserve available is 1332 MW.

Manager NEM Real Time Operations
     
X