Filter by category
Filter by Date
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120989 has been updated at 0100 hrs 27/11/2024 to the following:
[2.] From 0830 hrs 29/11/2024 to 1130 hrs 29/11/2024.
The forecast capacity reserve requirement is 1650 MW.
The minimum capacity reserve available is 1467 MW.
[3.] From 1330 hrs 29/11/2024 to 1900 hrs 29/11/2024.
The forecast capacity reserve requirement is 1487 MW.
The minimum capacity reserve available is 700 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120988 has been updated at 0100 hrs 27/11/2024 to the following:
[1.] From 1200 hrs 28/11/2024 to 2130 hrs 28/11/2024.
The forecast capacity reserve requirement is 1367 MW.
The minimum capacity reserve available is 489 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period[s]:
[1.] From 1700 hrs 28/11/2024 to 1800 hrs 28/11/2024.
The forecast capacity reserve requirement is 776 MW.
The minimum capacity reserve available is 728 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Cancellation of Actual (LOR1) condition in the NSW region - 26/11/2024
Cancellation of Actual (LOR1) condition in the NSW region - 26/11/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121009 is cancelled at 2015 hrs 26/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 886 MW
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120972 is cancelled at 16:50 hrs 26/11/2024.
No LOR2 condition is currently forecast in the STPASA period.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120981 has been updated at 1550 hrs to the following:
[1.] From 1630 hrs 26/11/2024 to 1930 hrs 26/11/2024.
The forecast capacity reserve requirement is 1380 MW.
The minimum capacity reserve available is 989 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120984 is cancelled at 1545 hrs 26/11/2024.
Manager NEM Real Time Operations
[EventId:202411261500_confirmed] Prices for interval 26-Nov-2024 15:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1520 hrs on 26 November 2024
PRICES ARE NOW CONFIRMED for trading interval 26-Nov-2024 15:00.
In accordance with Market Notice 120986 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.