120993RESERVE NOTICE26/11/2024 04:06:01 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120922 has been updated at 1400 hrs 26/11/2024 to the following:

1. From 0500 hrs 28/11/2024 to 0600 hrs 28/11/2024.
The forecast capacity reserve requirement is 1829 MW.
The minimum capacity reserve available is 1731 MW.

2. From 2300 hrs 28/11/2024 to 2359 hrs 28/11/2024.
The forecast capacity reserve requirement is 1712 MW.
The minimum capacity reserve available is 1231 MW.


AEMO Operations
     
120991RESERVE NOTICE26/11/2024 04:07:07 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120925 has been updated at 1400 hrs 26/11/2024 to the following:

1. From 1500 hrs 28/11/2024 to 1530 hrs 28/11/2024.
The forecast capacity reserve requirement is 881 MW.
The minimum capacity reserve available is 867 MW.

2. From 1630 hrs 28/11/2024 to 2030 hrs 28/11/2024.
The forecast capacity reserve requirement is 1234 MW.
The minimum capacity reserve available is 968 MW.


AEMO Operations
     
120989RESERVE NOTICE26/11/2024 04:08:09 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120978 has been updated at 1500 hrs 26/11/2024 to the following:

From 0630 hrs to 1500 hrs 29/11/2024.
The forecast capacity reserve requirement is 1421 MW.
The minimum capacity reserve available is 1200 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
120988RESERVE NOTICE26/11/2024 04:04:31 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120969 has been updated at 1500 hrs 26/11/2024 to the following:

1. From 0830 hrs to 1000 hrs 28/11/2024.
The forecast capacity reserve requirement is 1340 MW.
The minimum capacity reserve available is 1294 MW.

2. From 1030 hrs to 2300 hrs 28/11/2024.
The forecast capacity reserve requirement is 1523 MW.
The minimum capacity reserve available is 213 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
120984RESERVE NOTICE26/11/2024 02:39:39 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120980 has been updated at 1435 hrs to the following:

[1.] From 1730 hrs 26/11/2024 to 1800 hrs 26/11/2024.
The forecast capacity reserve requirement is 908 MW.
The minimum capacity reserve available is 847 MW.

AEMO is seeking a market response.

AEMO estimates the latest time at which it would need to intervene through an AEMO intervention event is 1730 hrs on 26/11/2024.

Manager NEM Real Time Operations
     
120983RECLASSIFY CONTINGENCY26/11/2024 02:27:31 PM

Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Duration: 26/11/2024 14:27 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
120981RESERVE NOTICE26/11/2024 02:05:17 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120954 has been updated at 1355 hrs to the following:

[1.] From 1630 hrs 26/11/2024 to 1730 hrs 26/11/2024.
The forecast capacity reserve requirement is 1380 MW.
The minimum capacity reserve available is 789 MW.

[2.] From 1800 hrs 26/11/2024 to 2000 hrs 26/11/2024.
The forecast capacity reserve requirement is 1690 MW.
The minimum capacity reserve available is 1001 MW.

Manager NEM Real Time Operations
     
120980RESERVE NOTICE26/11/2024 02:03:53 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120967 has been updated at 1355 hrs to the following:

[1.] From 1730 hrs 26/11/2024 to 1800 hrs 26/11/2024.
The forecast capacity reserve requirement is 761 MW.
The minimum capacity reserve available is 736 MW.

AEMO is seeking a market response.

AEMO estimates the latest time at which it would need to intervene through an AEMO intervention event is 1600 hrs on 26/11/2024.

Manager NEM Real Time Operations
     
120978RESERVE NOTICE26/11/2024 01:57:55 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120971 has been updated at 1300 hrs on 26/11/2024 to the following:

From 0630 hrs to 1330 hrs 29/11/2024.
The forecast capacity reserve requirement is 1269 MW.
The minimum capacity reserve available is 1217 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     