120710RECLASSIFY CONTINGENCY20/11/2024 01:46:31 PM

Reclassification of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE

Duration: 20/11/2024 13:46 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
120708RECLASSIFY CONTINGENCY20/11/2024 12:18:43 PM

Reclassification of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV

Duration: 20/11/2024 12:18 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
120690PRICES SUBJECT TO REVIEW19/11/2024 06:15:23 PM

[EventId:202411191820_review] Prices for interval 19-Nov-2024 18:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1815 hrs on 19 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 19-Nov-2024 18:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120689PRICES SUBJECT TO REVIEW19/11/2024 06:10:21 PM

[EventId:202411191815_review] Prices for interval 19-Nov-2024 18:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1810 hrs on 19 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 19-Nov-2024 18:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120688PRICES SUBJECT TO REVIEW19/11/2024 06:05:24 PM

[EventId:202411191810_review] Prices for interval 19-Nov-2024 18:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1805 hrs on 19 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 19-Nov-2024 18:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120686PRICES SUBJECT TO REVIEW19/11/2024 06:01:54 PM

[EventId:202411191805_review] Prices for interval 19-Nov-2024 18:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 19 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 19-Nov-2024 18:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120685PRICES SUBJECT TO REVIEW19/11/2024 05:55:24 PM

[EventId:202411191800_review] Prices for interval 19-Nov-2024 18:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1755 hrs on 19 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 19-Nov-2024 18:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120683PRICES SUBJECT TO REVIEW19/11/2024 05:50:24 PM

[EventId:202411191755_review] Prices for interval 19-Nov-2024 17:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1750 hrs on 19 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 19-Nov-2024 17:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120678MARKET SYSTEMS19/11/2024 03:35:12 PM

INC0138395 - P1 - Electricity Market Management System service- RESOLVED

AEMO ELECTRICITY MARKET NOTICE

This incident has been uplifted to a P1.

The service interruption relating to the Electricity Market Management System service has been resolved.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm