Filter by category
Filter by Date
Cancellation of Actual (LOR1) condition in the QLD region - 07/11/2024
Cancellation of Actual (LOR1) condition in the QLD region - 07/11/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.120112 is cancelled at 2010 hrs 07/11/2024.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 07/11/2024
Cancellation of Actual (LOR1) condition in the NSW region - 07/11/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.120113 is cancelled at 1945 hrs 07/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1430 MW
The minimum capacity reserve available is 1201 MW
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 07/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 07/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1090 MW
The minimum capacity reserve available is 897 MW
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 7 November 2024
NON-CONFORMANCE NSW1 Region Thursday, 7 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 07/11/2024 14:35 to 07/11/2024 15:05
Amount: -32 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 7 November 2024
NON-CONFORMANCE NSW1 Region Thursday, 7 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 07/11/2024 09:00 to 07/11/2024 10:45
Amount: -50 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Project Energy Connect (PEC-1) testing on 6th November 2024
Refer to market notice 119963
The Project Energy Connect (PEC-1) testing on 6th November has now been cancelled.
Terry Liu
AEMO Operations
Correction to testing time for Project Energy Connect (PEC-1) 6th November 2024 for flows in both directions
Refer to market notice 119961
This is correction to Project Energy Connect (PEC-1) testing time issued in previous notice 119961.
Testing time is on 6th November from 11:00 hrs to 22:00 hrs.
The test is for flows in both directions up to 50 MW. This test includes a trip and reclose of a line in South Australia. Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Mya San
AEMO Operations
Revised testing time for Project Energy Connect (PEC-1) 6th November 2024 for flows in both directions
Refer to market notice 119901
The Project Energy Connect (PEC-1) testing opportunity has changed ans it is now on 6th November at 22:00 hrs.
The test is for flows in both directions up to 50 MW.
This test includes a trip and reclose of a line in South Australia.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Terry Liu
AEMO Operations