121563RESERVE NOTICE07/12/2024 06:49:09 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121558 has been updated at 0645 hrs to the following:

[1.] From 1730 hrs 07/12/2024 to 1830 hrs 07/12/2024.
The forecast capacity reserve requirement is 1786 MW.
The minimum capacity reserve available is 1760 MW.

Manager NEM Real Time Operations
     
121558RESERVE NOTICE07/12/2024 04:21:32 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121550 has been updated at 0400 hrs to the following:

[1.] From 1630 hrs 07/12/2024 to 1900 hrs 07/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1284 MW.

Manager NEM Real Time Operations
     
121550RESERVE NOTICE06/12/2024 09:30:33 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1600 hrs 07/12/2024 to 1700 hrs 07/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1126 MW.

Manager NEM Real Time Operations
     
121530RESERVE NOTICE06/12/2024 04:44:35 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 06/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121529 is cancelled at 1645 hrs 06/12/2024.

Manager NEM Real Time Operations
     
121529RESERVE NOTICE06/12/2024 04:20:58 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121527 has been updated at 1620 hrs to the following:

[1.] From 1730 hrs 06/12/2024 to 1800 hrs 06/12/2024.
The forecast capacity reserve requirement is 1643 MW.
The minimum capacity reserve available is 1610 MW.

Manager NEM Real Time Operations
     
121527RESERVE NOTICE06/12/2024 03:55:14 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1630 hrs 06/12/2024 to 1830 hrs 06/12/2024.
The forecast capacity reserve requirement is 1626 MW.
The minimum capacity reserve available is 1296 MW.

Manager NEM Real Time Operations
     
121504RESERVE NOTICE06/12/2024 01:25:11 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1730 hrs 06/12/2024 to 1830 hrs 06/12/2024.
The forecast capacity reserve requirement is 1724 MW.
The minimum capacity reserve available is 1675 MW.

Manager NEM Real Time Operations
     
121490MARKET SYSTEMS05/12/2024 04:10:19 PM

CHG0100220 | Pre-Production | Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages

Change Number: CHG0100220

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Electricity Market Management System_PreProd

Change Title: Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages

Change Start Date & Time: 09/12/2024 08:00:00 AEST
Change End Date & Time: 10/12/2024 23:00:00 AEST
Outage Start Date & Time: 09/12/2024 08:00:00 AEST
Outage End Date & Time: 10/12/2024 23:00:00 AEST

Environment: Pre-Production

Participant Impact and Requirements: This Maintenance activity may cause intermittent outages to below applications during the outage period .

Impacted Systems:
1.EMMS systems (Dispatch/ PASA/ Forecasting/ Settlements)
2.Identity Service will be running only for authentication purposes.
3.Web Portal including menu items (Markets, Internal & Public portal)
4.GSH
5.GBB
6.Any GAS systems that have a NEMA / WARA database connection.
7.MSATS
8.CDR
9.DERR

If any ongoing issues are identified, please contact the AEMO Support Hub 1300 236 600.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
121468CONSTRAINTS09/12/2024 09:04:22 AM

Update to system strength requirements in North Queensland

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 106175

AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
Due to commissioning of Clarke Creek wind farm in Far North Queensland, the system normal equations have been revised.



A revision to the constraint equations will be implemented at 1100 hrs on Monday 9th December 2024.

The new combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

This advice contains all the combinations for Queensland for system normal cases. Additional information has been included in the limit advice to clarify the requirement to disconnect all inverters/turbines under certain system conditions.

The constraint equation in the Q-NIL set of the form below will be modified:

-Q_NIL_STRGTH_KBWF
-Q_NIL_STRGTH_MEWF

Two new equations have been added:

-Q_NIL_STRGTH_CKWF
-Q_NIL_STRGTH_CKWF_I